Our Expert in Lebanon
No results available
Last updated: August 25, 2026. Check for legislative or administrative updates before relying on any deadline calculation.
Lebanon’s Law No. 46/2026 (قانون تعليق المهل القانونية والقضائية والعقدية), enacted on 27 July 2026 and published in Official Gazette No. 32 on 30 July 2026, introduced a retroactive suspension of specified legal, judicial and contractual deadlines for the period from 1 March 2026 through 31 July 2026. The suspension period has now ended: affected deadlines resumed on 1 August 2026, with the balance remaining as at 1 March 2026 generally continuing from that date. The immediate issue for in-house counsel, general counsel and contract managers is therefore not how to prepare for a future lifting of the suspension, but how to identify and act on residual periods that have been running since 1 August—and to distinguish them from deadlines that had already expired before 1 March 2026.
This guide focuses on commercial contracts governed by Lebanese law. It explains the statute’s practical effect on notice periods, cure periods, performance milestones and prescription periods; highlights the relevance of Law No. 328/2024 and Constitutional Council Decision No. 2/2025; addresses force majeure and the absence of a general statutory hardship doctrine; and provides an updated compliance checklist and drafting templates.
TL;DR: Law No. 46/2026 suspended relevant legal, judicial and contractual deadlines retroactively from 1 March through 31 July 2026. The clock resumed on 1 August 2026. A period that had already expired before 1 March was not revived; a period that was still running on 1 March was paused and resumed from its remaining balance on 1 August.
The law suspends the running of relevant deadlines falling within the statutory scheme. For commercial purposes, the principal categories are:
The statute should not be read as a blanket rule that every time limit administered by every public authority automatically stops. The Ministry of Finance, for example, has published a detailed schedule for tax and fee obligations affected by Law No. 46/2026, and the NSSF has issued Memorandum No. 843 applying the law to relevant social-security deadlines. Those administrative measures are important in their own right and should be checked when dealing with public-law obligations.
The Chamber of Deputies adopted Law No. 46/2026 in its legislative session of 15 July 2026. It was promulgated as Law No. 46 on 27 July 2026 and published in Official Gazette No. 32 on 30 July 2026. The law nevertheless operates retroactively from 1 March 2026 through 31 July 2026.
The immediately relevant precedent is Law No. 328/2024 and Constitutional Council Decision No. 2/2025 of 16 January 2025. The Constitutional Council partially annulled Law No. 328/2024, including its retroactive suspension of certain judicial deadlines and the provision that would have permitted reopening final judgments, while leaving intact the suspension of legal and contractual deadlines for the period covered by the surviving provisions. The decision is important because it illustrates the constitutional sensitivity of retroactive interference with judicial procedure and legal certainty. Law No. 46/2026 should therefore be applied by reference to its own text and period, rather than treated as a simple continuation of Law No. 328/2024.
Law No. 46/2026 is retroactive in operation but not a general revival mechanism. A deadline that would have expired between 1 March and 31 July 2026 is treated as suspended during that window. A deadline that had already expired in full before 1 March 2026 is not restarted by the law.
For a period that was running on 1 March, the practical calculation is therefore: identify the unused balance on 1 March, carry that balance through the suspension window, and resume counting from 1 August. The resulting date must still be checked against the contract, the governing procedural regime and any statutory exception.
The most important commercial effects concern breach notices, cure periods, delivery deadlines, option periods and other time-based contractual mechanisms.
Running deadlines were paused from 1 March through 31 July and resumed on 1 August. For example, if a 30-day cure period had 15 days remaining on 1 March, those 15 days resumed on 1 August and would ordinarily have expired by mid-August. As of 25 August 2026, that residual period should therefore be treated as expired unless the breach was cured, the parties agreed otherwise, the contract provides a different calculation, or another legal rule applies.
By contrast, a notice or contractual period that had already expired before 1 March is not revived. A 60-day termination notice that expired in February 2026 cannot be reopened merely because Law No. 46/2026 later suspended comparable periods.
The distinction matters particularly in disputes over statutory or contractual rights that fell due during the suspension. The law may protect a period that would otherwise have expired during the protected window, but it does not necessarily restore a substantive right whose underlying period had already ended before 1 March.
Assume a supply agreement requires delivery within 90 days of order confirmation. Sixty days had elapsed by 1 March 2026, leaving 30 days. The remaining 30 days were suspended during March–July and resumed on 1 August. On a straightforward calendar-day calculation, the residual period runs through August 2026. The buyer should not wait until the end of the month to document the position: it should issue any required notice, preserve evidence and calculate the contractual consequences under the agreement.
For agency and distribution agreements, the same analysis may affect annual renewal windows, minimum-purchase periods and performance-linked termination triggers. A performance period that was running on 1 March may have been paused, while a target or breach that was already complete before 1 March is not necessarily undone by the suspension.
Statutory limitation and prescription periods are among the most consequential deadlines affected by Law No. 46/2026. Where a running prescription period was suspended, the unused balance resumed on 1 August. Where the period had expired before 1 March, Law No. 46/2026 does not revive it.
This is a calculation exercise that should be performed claim by claim. Counsel should record the original start date, the amount of time elapsed by 1 March, the suspension period, the remaining balance and the resumed expiry date. Contractual time-bars should be analysed separately from statutory prescription because the contract may impose its own notice or claim requirements.
| Deadline | Effect of Law No. 46/2026 | Practical response |
| Judicial/procedural deadlines | Suspended only to the extent covered by the law; periods already expired before 1 March are not revived. | Recalculate immediately; consider protective filings or interim relief where legally available. |
| Contractual notice/cure/termination periods | Running periods were paused during 1 March–31 July and resumed on 1 August, subject to the contract and statutory exceptions. | Recalculate the residual balance and issue any required notice without delay. |
| Prescription/limitation periods | Running periods were paused during the statutory window; expired periods before 1 March are not restored. | Prepare a claim-by-claim deadline schedule and obtain local-law advice on any uncertainty. |
Suppose a commercial landlord served a termination notice with a 90-day window and the suspension window opened on 1 March when 50 days remained. Those 50 days were frozen during March–July and resumed on 1 August. On a simple calendar-day calculation, the residual period would expire in the second half of September 2026. The landlord should therefore recalculate the expiry date, issue any necessary post-resumption notice and preserve its position rather than treating the notice as either extinguished or automatically enforceable.
The same logic applies to a contractual cure period. If 10 days remained on 1 March, those 10 days resumed on 1 August and, absent a different contractual or statutory calculation, would have expired in August. A party seeking to terminate should verify the precise expiry date and all notice requirements before acting.
Law No. 46/2026 should not be treated as a statutory declaration that every contractual non-performance during the relevant period was a force majeure event. The statute suspended deadlines; it did not itself create a universal defence to non-performance.
Under the Lebanese Code of Obligations and Contracts, including Articles 254 and 341–342, force majeure may excuse non-performance where the legal requirements are met, including an external event beyond the obligor’s control that is unforeseeable and irresistible and makes performance impossible. The explanatory material surrounding Law No. 46/2026 may be relied on by parties as contextual evidence of exceptional circumstances, but it does not eliminate the need to establish the elements of the particular force majeure defence.
Where the contractual and statutory requirements are met, relief may include suspension or excuse of performance and exclusion of contractual damages, depending on the wording of the contract and applicable law. Where performance is possible but has become materially more onerous, the analysis is different.
Lebanese law does not provide a general statutory hardship (imprévision) doctrine for private-law contracts that automatically entitles a party to judicial rebalancing merely because performance has become excessively onerous. A contractual hardship clause can create a negotiated route to renegotiation or other agreed relief. Without such a clause, the principal statutory routes discussed in this context are force majeure/impossibility and applicable judicial grace periods, including those referred to in Articles 300(2) and 241(3).
Statutory suspension / force majeure incorporation:
“For the purposes of this Agreement, ‘Force Majeure Event’ shall include any statutory suspension of legal, judicial or contractual deadlines enacted by the Lebanese Parliament, including Law No. 46/2026 and any successor or extension legislation, provided that the affected party demonstrates the causal link required by applicable law between the underlying event and its inability to perform.”
Hardship renegotiation mechanism:
“Where the economic equilibrium of this Agreement is fundamentally altered by an event constituting hardship, either party may request renegotiation in writing within [30] days of the triggering event. The parties shall negotiate in good faith for [60] days. If no agreement is reached, either party may refer the matter to [arbitration/the competent Lebanese court] in accordance with the dispute-resolution provisions of this Agreement.”
These clauses are contractual drafting options, not statements that Lebanese law automatically supplies a hardship remedy.
“[Party] hereby gives notice, on a protective and without-prejudice basis, that it considers the deadline under Clause [●] of [Contract] to have been affected by Law No. 46/2026. [Party] reserves all rights, remedies and claims and does not waive any position concerning the calculation or applicability of the suspension.”
Practical point: Use where the calculation or applicability of the law is uncertain. The notice must still comply with the contract’s notice mechanics.
“[Party] hereby notifies [Counterparty] that a Force Majeure Event within the meaning of Clause [●] has occurred, namely [describe event]. Performance of [obligations] is prevented or delayed. [Party] will use reasonable endeavours to mitigate the impact and will provide updates at intervals of [14] days.”
Practical point: Describe the causal link and comply with any contractual notice period.
“Where a Force Majeure Event prevents or delays performance, the affected party’s obligations shall be suspended for the duration of the event plus a recommencement period of [●] days. No liquidated damages, penalties or default interest shall accrue during that suspension, to the extent permitted by applicable law.”
Practical point: Define the recommencement period and mitigation obligations precisely.
“If performance of this Agreement becomes excessively onerous due to events beyond a party’s reasonable control, either party may request renegotiation. The parties shall negotiate in good faith for [60] days. Failing agreement, the dispute may be referred to [arbitration/the competent Lebanese court] under Clause [●].”
Practical point: Because Lebanese law does not supply a general statutory hardship regime, this clause should expressly state the agreed consequences of failed renegotiation.
“Any deadline under this Agreement that is legally suspended by mandatory Lebanese legislation shall, to the extent permitted by that legislation, be extended or recalculated by the period prescribed by the applicable law.”
Practical point: Avoid drafting the clause as though every future suspension will necessarily operate in the same way as Law No. 46/2026.
“Nothing in this notice, correspondence or conduct shall constitute a waiver, admission or estoppel. All rights, claims, remedies and defences are expressly reserved.”
Practical point: Useful in correspondence, but not a substitute for complying with mandatory notice requirements.
The end of the suspension does not make earlier inaction risk-free. Parties should reassess claims, notices and interim-remedy needs immediately, particularly where a residual period has already expired or is about to expire.
For local institutional arbitration, the relevant Lebanese institution is the Lebanese Arbitration and Mediation Center of the Chamber of Commerce, Industry and Agriculture of Beirut and Mount Lebanon (LAMC), rather than the Beirut Bar Association.
The burden of establishing the facts supporting impossibility, force majeure or hardship relief remains with the party relying on that position. Maintain a dedicated file containing notices, correspondence, delivery records, financial evidence, mitigation steps and official publications or administrative guidance relevant to the suspension.
The principal risk has shifted from waiting for the suspension to lift to failing to recognise that it already did. Law No. 46/2026 protected relevant deadlines during 1 March–31 July 2026; residual periods have been running again since 1 August, and short balances may already have expired. A contract portfolio that was not recalculated after 1 August should be reviewed now.
The practical response is to audit the contract register, recalculate residual periods, issue any necessary notices, preserve evidence, verify public-law deadlines and renegotiate exposed commercial terms where appropriate. The law does not eliminate the need for contractual compliance, nor does it provide a general hardship remedy.
The checklist and drafting templates in this guide are starting points only. Whether a particular deadline was suspended, when it resumed and what remedy remains available can depend on the wording of the contract, the legal source of the deadline, any applicable exception and the procedural forum. Lebanese-law advice should be obtained for material or disputed positions.
This article was produced by Global Law Experts. For specialist advice on this topic, contact Cyrille Naffah at The Edge Law Firm, a member of the Global Law Experts network.
posted 5 minutes ago
posted 11 minutes ago
posted 25 minutes ago
posted 35 minutes ago
posted 54 minutes ago
posted 1 hour ago
posted 3 hours ago
posted 3 hours ago
posted 3 hours ago
posted 3 hours ago
posted 4 hours ago
posted 4 hours ago
No results available
Find the right Legal Expert for your business
Send welcome message