[codicts-css-switcher id=”346″]

Global Law Experts Logo
section 75 contracts act malaysia

Section 75, Contracts Act Malaysia: Liquidated Damages, Penalties and Drafting for Enforceability

By Global Law Experts
– posted 1 hour ago

Section 75 of the Contracts Act 1950 is the single most important provision governing liquidated damages and penalty clauses in Malaysia. Unlike English common law, which draws a rigid line between enforceable liquidated damages and void penalty clauses, Section 75 replaces that distinction with a statutory “reasonable compensation” test, a framework that has been reshaped significantly by Federal Court jurisprudence. This guide explains the current judicial approach, provides ready-to-use drafting templates for commercial transactions, and sets out worked numerical examples and litigation strategy for both claimants and defendants.

What Section 75 of the Contracts Act 1950 Says

Section 75 of the Contracts Act 1950 (Act 136) provides, in essence, that when a contract has been broken and a sum is named in the contract as the amount to be paid in case of breach, or as a penalty, the party complaining of the breach is entitled to receive “reasonable compensation not exceeding the amount so named … whether or not actual damage or loss is proved to have been caused thereby.” This language has three critical consequences for parties drafting or enforcing contracts under the section 75 contracts act framework in Malaysia.

  • No penalty–liquidated damages distinction. The statute treats both identically. A clause labelled “penalty” and one labelled “liquidated damages” are governed by the same reasonableness standard.
  • Compensation is capped. The court may award less than the stipulated sum, but never more. The named amount operates as a ceiling.
  • Actual loss need not be proved. The innocent party is not required to adduce proof of actual loss, although evidence of loss remains relevant to the reasonableness assessment.

Practical takeaway: Labelling a clause “liquidated damages” or “penalty” has no legal effect on enforceability. What matters is whether the sum named is reasonable in the circumstances, a question ultimately determined by the court.

In the sections below, readers will find a detailed analysis of court principles, a cross-jurisdictional comparison table, three sample clauses with commentary, worked calculation examples, and a litigation evidence playbook.

How Courts Apply Section 75 of the Contracts Act, Core Principles and Burden of Proof

Core Principles: Reasonable Compensation Without Proof of Actual Loss

The Federal Court has confirmed that Section 75 of the Contracts Act 1950 allows reasonable compensation to be awarded irrespective of whether actual loss or damage is proven. The phrase “whether or not actual damage or loss is proved to have been caused thereby” means exactly what it says: the innocent party does not carry a mandatory burden to quantify its loss before recovering under a damages or penalty clause.

However, the compensation awarded must still be “reasonable.” Courts assess reasonableness by reference to proportionality, the commercial context, the parties’ bargaining positions at the time of contracting, and the legitimate interests the clause was designed to protect. Industry observers note that Malaysian courts have, since 2018, taken a more liberal view of the enforceability of stipulated sums, provided those sums fall within the bounds of commercial reasonableness.

  • No automatic entitlement to the full sum. The court retains discretion to award any amount from zero up to the contractual cap.
  • Evidence of loss strengthens the claim. Although proof of actual loss is not mandatory, presenting it helps demonstrate that the sum claimed is reasonable.
  • Unconscionable sums will be reduced. If the stipulated amount is extravagant, exorbitant or unconscionable relative to the actual or anticipated loss, the court will reduce the award.

Practical takeaway: Even though actual loss need not be proved, claimants should still compile loss evidence. This makes it significantly harder for the defaulting party to argue that the sum is unreasonable.

Burden of Proof and How It Shifts

The Federal Court has established a two-step burden-of-proof framework under Section 75 of the Contracts Act 1950 that every litigator and in-house counsel must understand.

Step Who bears the burden What must be shown
Step 1 Innocent party (claimant) That a breach of contract occurred and the contract includes a clause stipulating a sum payable upon breach (whether labelled as liquidated damages or penalty).
Step 2 Defaulting party (defendant) That the stipulated sum is unreasonable, meaning it is extravagant, exorbitant or unconscionable in the circumstances.

Once the claimant establishes Step 1, the evidential burden shifts. It is for the party in breach to demonstrate that the sum should be reduced. This shifting burden gives significant procedural advantage to the party enforcing the clause, and it underscores the importance of careful drafting at the contracting stage.

Practical takeaway: If you are drafting the clause, ensure the sum can withstand judicial scrutiny by documenting how it was calculated. If you are defending against a claim, prepare evidence showing disproportionality between the stipulated sum and the actual or foreseeable loss.

Key Federal Court Treatment and Post-2018 Evolution

The landmark Federal Court decision in Cubic Electronics Sdn Bhd v Mars Telecommunications Sdn Bhd (decided in 2018) fundamentally reset how liquidated damages in Malaysia are assessed. The Federal Court held that Section 75 had done away with the common-law distinction between liquidated damages and penalties. It further ruled that there was no necessity for proof of actual loss or damage where an innocent party seeks to enforce a stipulated sum under Section 75.

Post-Cubic Electronics, practitioner commentary confirms that Malaysian courts have also applied Section 75 principles to the forfeiture of deposits. A deposit paid as a guarantee of performance remains subject to the court’s reasonableness review, meaning that even a “non-refundable” deposit clause may be reduced if the court finds the forfeiture amount disproportionate.

Early indications suggest that this judicial direction, treating all pre-agreed sums under a unified reasonableness test, has become well-entrenched in Malaysian commercial jurisprudence. The likely practical effect is that parties must now treat every stipulated-sum clause as potentially reviewable, regardless of its label.

Liquidated Damages vs Penalty in Malaysia, Comparison with Common Law

Understanding how the treatment of a penalty clause in Malaysia differs from the English common-law position is essential for any cross-border transaction or international joint venture governed by Malaysian law. The table below illustrates the key distinctions.

Topic English law (penalty doctrine) Malaysia (Section 75, Contracts Act 1950)
Default rule Courts may strike down a penalty clause entirely, leaving only an action for actual loss Courts award “reasonable compensation” up to the stipulated sum, the clause is never simply struck down
Penalty vs liquidated damages distinction Critical, courts classify each clause, and penalties are void Abolished, Section 75 treats both identically under the reasonableness test
Proof of loss Must show the clause is a genuine pre-estimate of loss to enforce it in full No need to prove actual loss; reasonableness is the governing standard
Court’s discretion Binary: enforce in full or strike down entirely Flexible: court may award any amount from zero to the contractual cap
Drafting implication Use “genuine pre-estimate” language; justify calculation in recitals Document commercial justification, include mitigation obligations, and retain negotiation evidence

Clauses That Commonly Attract Judicial Scrutiny

Three types of contractual provisions are most frequently challenged under the section 75 contracts act Malaysia framework:

  • Late-completion liquidated ascertained damages (LAD). Common in construction and procurement contracts. Courts scrutinise whether the daily or weekly rate bears a reasonable relationship to the employer’s foreseeable loss from delay.
  • Forfeiture deposit clauses. Property sale-and-purchase agreements and commercial leases often include deposits described as “non-refundable.” Post-Cubic Electronics, these remain subject to proportionality review.
  • Termination-triggered lump-sum payments. Technology licensing and distribution agreements sometimes impose a fixed sum upon early termination. If the sum exceeds the licensor’s realistic loss, it invites challenge.

When the Full Contractual Sum Will Be Awarded

Industry observers expect courts to uphold a stipulated sum in full when the amount was arrived at through genuine arm’s-length negotiation, supported by documentary evidence of the anticipated loss, and where the defaulting party cannot demonstrate that it is disproportionate or unconscionable. Conversely, a sum that is many times larger than the foreseeable loss, or one inserted in a contract of adhesion without negotiation, is likely to be reduced.

Drafting for Enforceability Under Section 75, Clause Bank and Checklist

Effective drafting is the single best defence against judicial reduction of a liquidated damages clause. The following three templates illustrate best-practice approaches that align with how Malaysian courts apply Section 75 of the Contracts Act 1950.

Clause A: Liquidated Damages for Delay

“In the event the Contractor fails to achieve Practical Completion by the Completion Date (as extended, if applicable), the Contractor shall pay to the Employer liquidated damages at the rate of RM [amount] per calendar day of delay, calculated from the day after the Completion Date to the date of Practical Completion. The parties acknowledge that this rate represents a genuine and reasonable pre-estimate of the loss the Employer anticipates suffering as a result of delay, including but not limited to loss of rental income, additional financing costs and management overhead.”

Commentary: Including a rationale clause that specifies the heads of loss strengthens enforceability. Define “Practical Completion” and “Completion Date” precisely to avoid ambiguity about when the obligation triggers.

Clause B: Staged Forfeiture Deposit

“The Purchaser shall pay a deposit of [X]% of the Purchase Price upon execution. In the event the Purchaser fails to complete the purchase through no fault of the Vendor, the Vendor shall be entitled to forfeit the deposit in the following staged manner: (i) [Y]% representing administrative and re-marketing costs; and (ii) a further amount up to a maximum of the full deposit, but only to the extent the Vendor demonstrates actual loss exceeding the amount in (i). The Vendor shall use reasonable endeavours to mitigate its loss.”

Commentary: Staged forfeiture and a built-in mitigation obligation make the clause far more defensible. This structure anticipates the court’s proportionality review and reduces the risk of the entire deposit being treated as excessive.

Clause C: Cap and Step-Down Formula

“The Licensee’s liability for early termination shall not exceed RM [cap amount]. The payable amount shall be calculated as the product of the Monthly Licence Fee multiplied by the number of unexpired months remaining in the Licence Term, subject to a step-down reduction of [Z]% for every completed year of the Term. The parties agree this formula reasonably reflects the Licensor’s diminishing loss exposure over the Term.”

Commentary: A step-down formula is particularly effective for long-duration contracts where the licensor’s loss naturally decreases over time. It signals commercial reasonableness to the court.

Negotiation and Evidence Checklist

Before any liquidated damages clause is signed, in-house counsel should compile the following evidence, which becomes critical if the clause is later challenged:

  • Commercial justification memo. A short internal document explaining why the stipulated sum was chosen, what heads of loss it covers, and how it was calculated.
  • Pre-estimate calculation. A spreadsheet or financial model showing the anticipated loss from breach (e.g., daily revenue impact, financing costs, staff redeployment expenses).
  • Risk allocation note. A record of the negotiation showing that both parties discussed and agreed the sum, ideally reflected in meeting minutes or correspondence.
  • Comparable benchmarks. Evidence of similar clauses in comparable contracts within the same industry or sector.

Red Flags That Invite Court Reduction

  • A single lump sum applied to breaches of varying severity
  • A sum that vastly exceeds any foreseeable loss at the time of contracting
  • Use of punitive language such as “penalty” or “forfeiture” without mitigation obligations
  • No documented commercial justification or negotiation history
  • A “take it or leave it” clause in a standard-form contract with no opportunity for negotiation

Calculating Reasonable Compensation Under Section 75, Worked Examples

Understanding how to calculate liquidated ascertained damages in Malaysia requires translating the legal principles into numbers. Below are two worked examples showing how courts might assess a claim.

Example 1: Delay in Delivery (Supply Contract)

A manufacturer agrees to deliver industrial equipment by 1 March. The purchase contract stipulates LAD at RM 5,000 per day of delay. Delivery occurs on 1 April, 31 days late.

  • Contractual claim: 31 days × RM 5,000 = RM 155,000
  • Buyer’s evidence of loss: Lost production revenue of RM 4,200/day (supported by management accounts) + additional rental of standby equipment at RM 600/day = RM 4,800/day foreseeable loss.
  • Court assessment: RM 5,000/day is close to the demonstrated daily loss of RM 4,800. The likely outcome is that the court upholds the full contractual sum, or awards a figure very close to it, because the per-day rate is not extravagant relative to the proven loss.

Key variables to document: daily revenue impact, cost of alternative supply, financing costs of delay, and management overhead.

Example 2: Forfeited Deposit (Property Transaction)

A purchaser pays a 10% deposit (RM 200,000) on a RM 2,000,000 commercial property. The purchaser defaults. The vendor claims full forfeiture.

  • Vendor’s actual loss: Re-marketing costs (RM 15,000), legal fees (RM 8,000), price difference on resale six months later (RM 50,000) = RM 73,000 total demonstrated loss.
  • Court assessment: RM 200,000 forfeiture versus RM 73,000 actual loss suggests the deposit is disproportionate. The court is likely to allow forfeiture of an amount reflecting demonstrated loss plus a reasonable margin, perhaps RM 90,000 to RM 110,000, and order the balance refunded.

Key variables to document: re-marketing expenses, price differential on resale, holding costs, legal and conveyancing fees, and time to resale.

Quick-Reference Calculation Variables

  • Daily/weekly/monthly revenue lost due to breach
  • Cost of alternative performance or substitute supply
  • Additional financing or interest costs
  • Administrative and legal costs of managing the breach
  • Difference between contract price and market price at the time of breach
  • Mitigation costs actually incurred

Litigation and Evidence Strategy, Defending or Attacking a Clause Under Section 75

Strategy for the Claimant (Seeking the Contractual Sum)

The claimant’s primary objective is to establish breach and the existence of the stipulated-sum clause, then resist any attempt by the defendant to prove the sum is unreasonable. Key evidence includes the signed contract containing the clause, proof of breach (notices, correspondence, inspection reports), the negotiation file showing both parties discussed and agreed the sum, and the commercial justification memo prepared at the time of drafting.

Strategy for the Defendant (Seeking Reduction)

The defendant must demonstrate that the stipulated sum is extravagant, exorbitant or unconscionable. Effective evidence includes proof of the claimant’s actual loss (or absence of loss), expert evidence on proportionality, evidence that the clause was imposed without negotiation (adhesion contract), and comparable contract data showing the sum is an outlier in the relevant industry.

Procedural Tips

Experienced practitioners advise pleading both the full contractual sum and, in the alternative, a claim for reasonable compensation under Section 75 of the Contracts Act. This preserves the claimant’s position even if the court reduces the stipulated amount. Expert evidence on quantum is often decisive, particularly in construction disputes where how to calculate liquidated ascertained damages in Malaysia depends on industry-specific variables.

Party Evidence to lead Purpose
Claimant Contract with clause, breach evidence, negotiation records, commercial justification memo, loss evidence (if available) Establish breach + clause existence; demonstrate reasonableness of stipulated sum
Defendant Proof of claimant’s actual loss (or absence thereof), expert report on proportionality, evidence of no negotiation, industry benchmarks Shift court’s assessment toward a lower “reasonable compensation” figure
Both Expert quantum evidence, comparable contracts, financial models Assist court in determining the “reasonable” figure within the statutory cap

Conclusion, In-House Counsel Action Checklist for Section 75 Contracts Act Malaysia

The section 75 contracts act Malaysia framework gives courts broad discretion to award any amount from zero to the contractual cap. The parties that fare best are those who prepare at the drafting stage, not the litigation stage. The following action checklist summarises the key steps:

  • Draft with evidence in mind. Include a rationale clause, define the heads of loss, and attach or reference the pre-estimate calculation.
  • Preserve the negotiation record. Keep minutes, correspondence and draft mark-ups showing that both parties discussed and agreed the sum.
  • Include mitigation obligations. A clause requiring the innocent party to mitigate signals commercial reasonableness.
  • Use caps and step-down formulae. These reduce the risk of the court finding the sum disproportionate, particularly in long-duration contracts.
  • Prepare for litigation from day one. Compile loss evidence contemporaneously, invoices, management accounts, comparable contracts, so it is available if the clause is later challenged.

Last reviewed: 24 May 2026. This guide will be updated following any new Federal Court decisions or legislative amendments affecting Section 75 of the Contracts Act 1950.

Need Legal Advice?

This article was produced by Global Law Experts. For specialist advice on this topic, contact Shanker Sivapragasam at MESSRS K.SILADASS & PARTNERS, a member of the Global Law Experts network.

Sources

  1. Contracts Act 1950 (Official Text PDF)
  2. Lee Hishammuddin Allen & Gledhill, Liquidated Damages: The Taming of Section 75
  3. Allen & Gledhill, Malaysian Federal Court Finds No Necessity for Proof of Actual Loss
  4. Skrine, Federal Court Restates the Law on Deposits and Damages Clauses
  5. Thomas Philip, Recoverability of Liquidated Ascertained Damages Clauses in Construction Contracts
  6. White & Case, Managing Construction Risks in Asia-Pacific: Malaysia
  7. Kevin Wu & Associates, Remedies for Breach of Contract under Malaysian Law
  8. University of Malaya Law Review, A Stunning Restatement of the Law on Liquidated Damages

FAQs

Can a penalty clause be enforced in Malaysia?
Yes. Under Section 75 of the Contracts Act 1950, a clause labelled “penalty” is not automatically void. The court will assess whether the sum is reasonable and may award compensation up to that amount, regardless of the label used.
A penalty clause is a contractual provision stipulating a sum payable upon breach. Unlike English law, Malaysian law under Section 75 does not distinguish between penalties and liquidated damages, both are subject to the same reasonableness test.
Not automatically. The court will not strike down a penalty clause entirely. Instead, it awards “reasonable compensation” up to the amount named in the contract. A sum that is extravagant or unconscionable will be reduced, but not voided.
No. The Federal Court has confirmed that proof of actual loss is not mandatory. However, presenting evidence of loss strengthens the claim for the full stipulated amount and makes it harder for the defendant to argue the sum is unreasonable.
Identify the foreseeable heads of loss (e.g., lost revenue, additional costs, financing charges), quantify each using financial data available at the time of contracting, and sum them. The total serves as the pre-estimate that justifies the stipulated rate or sum.
A rationale clause listing the heads of loss, a defined trigger mechanism, a mitigation obligation, a cap or step-down formula for long-term contracts, and a reference to the supporting pre-estimate calculation retained on file.
Not necessarily. The Federal Court has held that Section 75 applies to deposit forfeiture. If the deposit amount is disproportionate to the vendor’s actual or foreseeable loss, the court may order a partial refund, retaining only a reasonable portion.
patent enforcement in italy
By Global Law Experts

posted 2 minutes ago

how to apply for letters of administration in ireland online
By Global Law Experts

posted 3 hours ago

Find the right Legal Expert for your business

The premier guide to leading legal professionals throughout the world

Specialism
Country
Practice Area
LAWYERS RECOGNIZED
0
EVALUATIONS OF LAWYERS BY THEIR PEERS
0 m+
PRACTICE AREAS
0
COUNTRIES AROUND THE WORLD
0
Join
who are already getting the benefits
0

Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.

Naturally you can unsubscribe at any time.

Newsletter Sign Up
About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Global Law Experts App

Now Available on the App & Google Play Stores.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Contact Us

Stay Informed

Join Mailing List
About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Global Law Experts App

Now Available on the App & Google Play Stores.

Contact Us

Stay Informed

Join Mailing List

GLE

Lawyer Profile Page - Lead Capture
GLE-Logo-White
Lawyer Profile Page - Lead Capture

Section 75, Contracts Act Malaysia: Liquidated Damages, Penalties and Drafting for Enforceability

Send welcome message

Custom Message