Our Expert in Denmark
No results available
Denmark’s accelerating offshore‑wind programme has entered a decisive phase: new tender rounds launched in 2025–26, revised Contract‑for‑Difference (CfD) frameworks, and ambitious Power‑to‑X targets are generating some of the largest EPC projects in the country’s history. With that scale comes a sharp rise in offshore wind construction disputes in Denmark, particularly over who bears the cost of unforeseen seabed conditions, weather and supply‑chain delays, and grid‑connection shortfalls controlled by Energinet as the national transmission system operator (TSO). This guide provides a practical dispute playbook for project owners, EPC contractors, lenders, and in‑house counsel, covering risk allocation in contracts, notice and evidence requirements, and arbitration strategy tailored to the Danish regulatory and legal landscape.
Every section draws on the frameworks published by the Danish Energy Agency (Energistyrelsen), Energinet’s grid‑connection procedures, and Danish contract and arbitration law as consolidated on Retsinformation.
Understanding the regulatory backdrop is essential before drafting or defending any offshore wind contract in Denmark. The Danish Energy Agency oversees licensing, environmental impact assessment, and tender design, while Energinet is responsible for offshore grid infrastructure and connection timelines. Both institutions have published updated guidance in 2025–26 that directly shapes how risk is distributed in EPC and development agreements.
| Period | Rule / Change | Practical Effect on Risk Allocation |
|---|---|---|
| 2024–25 | Revised CfD tender framework, new risk‑sharing provisions introduced by the Danish Energy Agency | Developer revenue risk partially underwritten by the state; tender documents now require bidders to price geotechnical and grid‑interface risk explicitly |
| 2025 | Updated Energinet grid‑connection procedures and interface schedules | Clearer demarcation of TSO vs. developer responsibility for substation and cable‑route handover; tighter acceptance‑test timelines |
| 2025–26 | Tightened CO₂ reduction targets and expanded Power‑to‑X ambitions | Larger project scopes (multi‑GW tenders) increase overall contract value and claims quantum; new interface issues between wind farm and electrolyser/PtX infrastructure |
| 2026 | Ongoing consolidation of Danish contract and arbitration law on Retsinformation | Danish Arbitration Act continues to govern seat‑of‑arbitration and enforcement; contractual freedom remains the default for commercial EPC risk allocation |
The likely practical effect of these changes is that tender documents now function as a first layer of risk allocation, before any EPC contract is signed. Bidders who do not scrutinise tender‑level risk provisions may inherit obligations (particularly around seabed surveys and grid readiness) that are difficult to pass through to subcontractors. Industry observers expect this to increase the frequency and complexity of offshore wind construction disputes in Denmark through 2027 and beyond.
Subsurface conditions are the dominant technical uncertainty in offshore‑wind construction. Foundation design, monopile installation, and cable‑burial depths all depend on accurate knowledge of seabed geology. When the ground does not match what was expected, the cost consequences can reach tens of millions of euros, and the resulting dispute over geotechnical risk in Denmark typically turns on what the contract says about site investigation, what information was provided pre‑tender, and how the unforeseen‑conditions clause operates.
Danish law grants wide contractual freedom to commercial parties. Unlike some civil‑law jurisdictions, Denmark does not impose a statutory doctrine of changed circumstances that automatically entitles a contractor to additional payment when ground conditions differ from expectations. The parties must therefore allocate subsurface risk expressly in their contract. Where they fail to do so, the default position under general Danish contract principles, as reflected in case law accessible via Retsinformation, is that a contractor who undertakes a lump‑sum obligation bears the risk of conditions it could reasonably have foreseen.
The Danish standard‑form AB 18 (Almindelige Betingelser for arbejder og leverancer i bygge‑ og anlægsvirksomhed) provides a useful domestic comparison, although it was not designed for offshore energy projects. AB 18 allocates unforeseen subsurface risk primarily to the owner, provided the contractor could not have discovered the conditions through reasonable investigation. Offshore wind contracts in Denmark often modify or depart from AB 18 substantially, but its risk‑allocation logic remains a persuasive reference point in Danish arbitration.
A well‑drafted site investigation clause should prescribe the scope, quality, and ownership of all pre‑contract geotechnical data and define who pays for additional investigation during construction. The following checklist sets out best‑practice deliverables for Danish offshore projects:
The allocation decision is straightforward in principle: if the owner provides comprehensive site‑investigation data and the contractor is given the opportunity to verify it, residual subsurface risk can more defensibly sit with the contractor. If the owner provides limited data or restricts the contractor’s ability to conduct its own surveys, industry observers expect tribunals to treat the owner as bearing the risk of conditions that a fuller investigation would have revealed.
The following illustrative clause demonstrates how parties can address discovery risk. Drafting notes follow each operative provision:
“If, during the execution of the Works, the Contractor encounters physical conditions at the Site (other than weather or sea‑state conditions) that (a) could not reasonably have been foreseen by an experienced contractor having examined the Site Investigation Data listed in Schedule [X], and (b) materially affect the cost or time required for the execution of the Works, the Contractor shall be entitled to an extension of time and reimbursement of Cost, provided that the Contractor complies with the notice requirements of Clause [Y].”
Delay and disruption claims offshore present unique evidential challenges. Marine weather windows, vessel availability, and the interdependence of foundation installation, turbine erection, and cable laying mean that a single delay event can cascade through an entire programme. To preserve entitlement, whether claiming or defending, parties must build a robust contemporaneous record from day one.
Most Danish offshore wind contracts treat notice as a condition precedent to a claim for extension of time (EOT) or additional cost. Failure to give timely notice can extinguish the entitlement entirely, regardless of the merits. A compliant notice should include:
The baseline critical‑path method (CPM) schedule is the single most important document in any EPC claims Denmark dispute. Owners should require contractors to submit a fully logic‑linked, resource‑loaded baseline programme within 28 days of contract award and to update it monthly. The following contemporaneous records should be maintained alongside the CPM:
Danish contract law imposes a general obligation to mitigate loss. A contractor that fails to re‑sequence work, mobilise additional vessels, or explore alternative installation methods will find its delay claim reduced, even if the original delay event was entirely the owner’s fault. Owners, for their part, should ensure that liquidated damages (LDs) clauses are drafted as a genuine pre‑estimate of loss. Under Danish law, a court or tribunal may reduce LDs that are manifestly disproportionate, although the threshold for intervention is high in commercial contracts between sophisticated parties. Industry observers expect tribunals to scrutinise LD rates more carefully on multi‑GW projects where the absolute sums can be very large.
Grid connection delays in Denmark are among the most commercially significant risks in offshore‑wind construction, yet they are routinely under‑drafted. Energinet, as the Danish TSO, is responsible for designing, constructing, and commissioning the offshore grid infrastructure, including the offshore substation and export cable to shore in many configurations. The developer and EPC contractor depend on Energinet meeting its delivery schedule, but Energinet’s obligations run under a separate regulatory and contractual framework, not the EPC contract.
Energinet’s grid‑connection procedures, published on its official website, define the technical interface between the wind farm and the transmission system. Key interface points include the offshore substation (ownership boundary), the export cable landfall, and the onshore point of connection. Acceptance testing at each interface point is governed by Energinet’s technical regulations, which incorporate pan‑European network codes published by ENTSO‑E.
| Risk / Obligation | Owner / Developer | EPC Contractor | TSO (Energinet) |
|---|---|---|---|
| Grid infrastructure delivery | Monitor; notify contractor of TSO delays | No control; needs contractual relief | Design, construct, and commission on schedule |
| Interface acceptance testing | Coordinate between contractor and TSO | Prepare wind‑farm‑side equipment for testing | Conduct grid‑side acceptance tests per technical regulations |
| Delay costs (prolongation, idle vessels) | Bear if TSO delay is an owner‑risk event; claim against TSO under connection agreement | Entitled to EOT and cost only if contract provides relief for grid delays | Liable under connection agreement terms (often capped) |
| Revenue loss / CfD implications | Bear directly; may claim under connection agreement or insurance | Not typically liable for revenue loss | Regulatory remedies may apply |
The critical drafting point is whether the EPC contract treats a TSO grid delay as a relief event entitling the contractor to time (and potentially cost) or whether the contractor is expected to absorb the delay within its programme float. Best practice for offshore wind contracts in Denmark is to include an express grid‑delay relief clause that grants the contractor an EOT for any delay to the grid‑connection milestone caused by Energinet, together with recovery of demonstrable prolongation costs. Owners can manage this exposure by negotiating back‑to‑back provisions in the Energinet connection agreement or by procuring delay‑in‑start‑up (DSU) insurance.
Winning or defending an offshore wind construction dispute depends as much on the quality of evidence as on the merits of the legal argument. This section sets out the evidence plan and quantum methodology that claim teams should follow from the start of construction.
| Claim Head | Key Evidence | Calculation Method |
|---|---|---|
| Unforeseen ground conditions, additional foundation cost | CPT logs, borehole data, as‑built records, variation orders | Actual cost vs. tendered cost for affected foundations; supported by geotechnical expert report |
| Prolongation (time‑related cost) | CPM schedule updates, daily logs, vessel hire records | Time‑impact analysis identifies EOT; prolongation cost = site overhead × delay period |
| Disruption (loss of productivity) | Planned vs. actual productivity records, crew reports, weather logs | Measured‑mile analysis or earned‑value comparison |
| Grid‑connection delay, idle vessel and standby cost | Energinet milestone correspondence, vessel charter agreements, standby logs | Vessel day‑rate × idle days; plus crew and insurance costs during standby |
Arbitration is the standard dispute‑resolution mechanism for large offshore‑wind EPC contracts. It offers confidentiality, the ability to appoint technically qualified arbitrators, and enforceability of awards across the EU under the New York Convention and, within Denmark, the Danish Arbitration Act as published on Retsinformation.
Copenhagen is the natural seat for arbitration offshore wind Denmark disputes, although parties with multi‑jurisdictional supply chains sometimes choose a neutral seat. Danish law is typically the governing law for contracts with a Danish developer. Emergency arbitrator provisions, available under leading institutional rules, allow parties to obtain provisional measures (for example, orders to preserve evidence or continue interim payments) before the full tribunal is constituted.
The following escalation ladder reflects best practice in Danish offshore‑wind EPCs:
Practitioners should consider whether to bifurcate proceedings into liability and quantum phases. Bifurcation can reduce costs if the liability defence is strong, but it adds time if both phases proceed. The appointment of tribunal‑appointed technical experts, rather than relying solely on party‑appointed experts, can narrow technical disputes and accelerate resolution. Awards seated in Denmark are enforceable across the EU under Regulation (EU) 1215/2012 and internationally under the New York Convention, as facilitated by the Danish Arbitration Act and overseen by the Danish Bar and Law Society (Advokatsamfundet).
The following annotated clauses are designed to be adapted for use in Danish offshore‑wind EPC contracts. Each clause addresses one of the three primary dispute categories covered in this guide.
“The Owner shall provide to the Contractor, no later than [X] days prior to the Commencement Date, all Site Investigation Data identified in Schedule [A], including geophysical survey reports, geotechnical borehole logs, CPT results, and UXO survey data. The Contractor shall be entitled to conduct verification investigations at the Owner’s cost, provided such investigations are reasonably necessary and do not unreasonably delay the Works.”
Drafting note: Defining the data package in a schedule prevents disputes over whether the contractor received “sufficient” information. The verification right, at the owner’s cost, incentivises the owner to provide complete data upfront.
“Where the Contractor encounters Subsurface Conditions that differ materially from those indicated in the Site Investigation Data, and which an experienced offshore contractor could not reasonably have foreseen, the Contractor shall give notice under Clause [Y] within 14 days. The Contractor’s entitlement shall be limited to the net additional Cost and an extension of time to the extent that such conditions cause delay to the Critical Path.”
Drafting note: “Net additional cost” ensures the contractor deducts any savings from changed conditions elsewhere. The critical‑path linkage prevents time claims for delays to non‑critical activities.
“If the TSO Grid‑Connection Milestone is delayed beyond the date stated in Schedule [B] for reasons not attributable to the Contractor, the Contractor shall be entitled to (a) an extension of time equal to the period of such delay, and (b) reimbursement of demonstrable prolongation Costs including vessel standby charges. The Owner shall use reasonable endeavours to recover such Costs from the TSO under the Connection Agreement.”
Drafting note: This clause places grid‑delay risk on the owner (who controls the TSO relationship) while requiring the contractor to demonstrate actual costs. The “reasonable endeavours” recovery obligation aligns the owner’s incentives to enforce the connection agreement.
| Entity | Typical Contractual Reporting Obligations | Practical Consequences for Claims |
|---|---|---|
| Owner / Developer | Provide site access, permit documentation, baseline project data, and pre‑contract geotechnical reports (if any) | Failure to disclose exposes the owner to liability for delays and costs linked to withheld information; tribunals review disclosure reasonableness |
| EPC Contractor | Produce detailed SI plan, baseline schedule, daily logs, CPM updates, and written notice of unforeseen conditions | Failure to produce contemporaneous records substantially weakens entitlement to EOT and additional costs |
| TSO / Energinet | Provide grid acceptance schedule, technical interface specifications, and readiness confirmations | Delays at the TSO interface are usually outside contractor control, the contractor needs a clear relief and payment mechanism to avoid being charged liquidated damages |
As Denmark’s offshore‑wind pipeline expands through 2026 and beyond, the volume and complexity of offshore wind construction disputes in Denmark will grow in parallel. The projects are larger, the regulatory framework is evolving, and the interfaces between developers, EPC contractors, and Energinet are more intricate than ever. Parties that invest in clear contractual drafting, particularly around geotechnical risk, delay entitlements, and grid‑connection allocation, and that maintain rigorous contemporaneous records from the first day of construction will be far better positioned to resolve claims efficiently, whether through negotiation, expert determination, or arbitration.
This article was produced by Global Law Experts. For specialist advice on this topic, contact Christian Johansen at Bruun & Hjejle, a member of the Global Law Experts network.
posted 21 minutes ago
posted 1 hour ago
posted 2 hours ago
posted 2 hours ago
posted 2 hours ago
posted 2 hours ago
posted 3 hours ago
posted 3 hours ago
posted 4 hours ago
posted 4 hours ago
posted 4 hours ago
posted 5 hours ago
No results available
Find the right Legal Expert for your business
Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.
Naturally you can unsubscribe at any time.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Send welcome message