How to Commence Construction Arbitration in Canada (step‑by‑step, 2026 Update)

By Global Law Experts
– posted 1 hour ago

Understanding how to commence construction arbitration in Canada is essential for any contractor, subcontractor or owner facing a payment dispute, deficiency claim or delay conflict on a Canadian project. Arbitration offers a private, binding alternative to court litigation, one that allows the parties to select a decision‑maker with genuine construction expertise and to resolve the matter on a confidential, typically faster track. This guide sets out every step in the process, from reviewing the contract and serving the first notice through to the hearing and enforcement of the award, while integrating the 2026 prompt‑payment and adjudication amendments that now affect dispute‑resolution strategy in Ontario, British Columbia and other provinces.

Whether you are an in‑house counsel mapping options for the first time or a project manager who has just received a notice, this article provides the checklists, timelines, documents and cost estimates you need to act with confidence.

Overview of the Construction Arbitration Process and Who It Applies To

Construction arbitration is a consensual, contractually driven process in which one or more independent arbitrators hear evidence and issue a binding award. Unlike litigation, the proceeding is private, the tribunal can be chosen for its industry knowledge, and the timetable is typically set by the parties rather than by court schedules. Unlike the newer statutory adjudication regimes now operating in several provinces, arbitration produces a final and binding decision, not an interim determination, and can address the full range of claims: payment, delay, defects, professional negligence, back‑charges and termination disputes.

When to Choose Arbitration Over Adjudication or Litigation

Arbitration is appropriate when the construction contract contains an arbitration clause (or the parties agree to arbitrate after the dispute arises), when the dispute involves complex factual or technical issues better suited to an expert tribunal, and when confidentiality matters. If the primary concern is speed of cash flow, the prompt‑payment adjudication process may deliver a faster interim remedy; however, the adjudication decision can subsequently be referred to arbitration for final determination. Litigation remains relevant where injunctive relief is urgent or where lien enforcement under the applicable provincial Construction Act requires court proceedings.

The steps to start arbitration covered in this guide are as follows:

  • Confirm eligibility and contractual prerequisites
  • Review the contract and collect evidence
  • Serve a Notice of Dispute or Notice of Arbitration
  • File with the chosen institution and pay initial fees
  • Appoint the arbitrator or tribunal
  • Seek interim measures or emergency relief (if needed)
  • Manage the procedural timetable, document exchange and experts
  • Attend the hearing, obtain the award and take post‑award steps

Eligibility and Construction Arbitration Canada Requirements

Before commencing arbitration, confirm that the dispute is eligible and that all contractual prerequisites have been satisfied. Failing to do so is one of the most common, and most costly, mistakes parties make.

Contractual Prerequisites

Locate the arbitration clause in the prime contract or subcontract. Identify the seat of arbitration (the legal jurisdiction), the governing institutional rules (e.g., ADR Institute of Canada Arbitration Rules or ICDR Canada Rules), the number of arbitrators, and any mandatory pre‑conditions such as a written notice of dispute, a negotiation period or a mediation step. Multi‑party and joinder provisions are critical on projects with multiple subcontractors, if the clause does not permit joinder, you may face parallel proceedings.

Non‑Arbitrable Matters

Certain matters cannot be referred to arbitration under Canadian law. The federal Commercial Arbitration Act and equivalent provincial statutes adopt the UNCITRAL Model Law framework, which preserves court jurisdiction over constitutional questions and certain public‑law issues. Specific insolvency proceedings and some statutory lien‑enforcement steps must also proceed in court. Verify with the applicable provincial arbitration statute before filing.

Pre‑Filing Checklist

  • Confirm the arbitration clause. Record the clause number, seat, rules and any escalation steps.
  • Confirm governing law and limitation period. Limitation periods vary by province, verify with counsel.
  • Preserve evidence. Secure site diaries, photos, payment records and correspondence immediately.
  • Preserve lien and holdback rights. Under Ontario’s amended Construction Act (effective 1 January 2026), holdback and prompt‑payment obligations interact with arbitration timing. Failure to preserve lien rights may affect security.

Step‑by‑Step Procedure to Commence Construction Arbitration in Canada

The following numbered steps walk through the full process from contract review to award. Timelines are estimates; verify each against the applicable institutional rules and provincial statutes.

Step 1: Review the Contract and Collect Evidence

Begin by reading the arbitration clause in full. Note the seat, the applicable rules, any emergency‑arbitrator provision, and the method and address for service of notices. Gather all contemporaneous project records: invoices, pay applications, change orders, daily reports, photographs, test results, subcontract packages, meeting minutes and relevant correspondence. Organise these chronologically and electronically, they will form the documentary backbone of the case.

A sample notice‑of‑dispute opening line, adapted for Canadian construction contracts, reads: “Pursuant to clause [X] of the Contract dated [date], [Claimant] hereby gives notice of a dispute arising from [brief description of dispute] and invokes the arbitration provisions therein.”

Step 2: Serve a Notice of Dispute or Notice of Arbitration

The distinction between a “notice of dispute” and a “notice of arbitration” (sometimes called a “request for arbitration”) matters. Many construction contracts require the claimant to serve a notice of dispute first, triggering a negotiation or mediation window, before formal arbitration can begin. Failing to comply with this condition precedent may allow the respondent to challenge jurisdiction.

When the contractual preconditions are satisfied, prepare the formal Notice of Arbitration. Under most institutional rules, this document must contain:

  • Full names and contact details of all parties
  • A copy of (or reference to) the arbitration clause
  • A summary of the facts giving rise to the claim
  • The relief sought and an estimate of the amount in dispute
  • The seat and language of arbitration
  • The proposed number of arbitrators and any nomination

Serve the notice by the method the contract specifies (registered mail, courier, email to a contractual address). Retain proof of service, an affidavit of service or a delivery receipt, in every case. Under the ICDR Canada Arbitration Rules, filing fees are payable upon submission of the notice. Under the ADR Institute of Canada Arbitration Rules, the notice triggers the institution’s administrative process and a corresponding fee.

Step 3: File with the Institution and Pay Initial Fees

If the contract designates an administering institution (ADRIC, ICDR Canada, ICC or AAA/ICDR), submit the Notice of Arbitration together with the filing fee and any required number of copies. The ICDR Canada fee schedule sets initial filing and administrative fees on a sliding scale based on claim amount. ADRIC offers a simplified arbitration track with lower fees for smaller claims. Ensure the filing is complete: a deficient filing, missing fee payment, unsigned notice, or incomplete party details, will delay commencement and may prejudice limitation periods.

Practical action checklist at this stage:

  • Prepare a fee‑budget estimate covering filing, administration and anticipated arbitrator deposits
  • Identify whether joinder of additional parties (e.g., subcontractors, sureties) is needed and check institutional joinder rules
  • Calendar the institution’s response deadlines for the respondent

Step 4: Appoint the Arbitrator(s)

The appointment method depends on the contract and the institutional rules. Common options include:

  • Party appointment. Each party nominates one arbitrator; the two party‑appointed arbitrators select a presiding arbitrator.
  • Institutional appointment. The institution appoints from its panel, often after consulting the parties’ preferences.
  • Sole arbitrator. Agreed by the parties or appointed by the institution, common for disputes under a specified monetary threshold.

In construction arbitration, the selection criteria are critical. Industry observers expect the most effective tribunals to combine legal expertise with hands‑on construction knowledge, a practising engineer or quantity surveyor sitting alongside a legally qualified chair, for example. Request CVs, check for conflicts of interest, and use the institution’s challenge mechanism if independence or impartiality is in doubt. Appointment typically takes 14–60 days, though expedited procedures can shorten this to days.

Step 5: Seek Interim Measures and Emergency Relief

Interim measures in arbitration may be necessary to preserve the status quo while the tribunal is constituted. Common examples include injunctions to prevent asset dissipation, freezing orders, preservation‑of‑evidence orders and security‑for‑costs applications. Two routes are available:

  • Emergency arbitrator. Many institutional rules (including ICDR Canada) provide for an emergency arbitrator who can be appointed within days and grant provisional relief before the full tribunal is in place.
  • Court application. The Commercial Arbitration Act and its provincial equivalents expressly permit a party to apply to court for interim measures without waiving the right to arbitrate. Courts routinely grant conservatory relief in construction disputes, for example, orders preserving disputed funds or preventing demolition of works under inspection.

Where prompt‑payment adjudication has been commenced in parallel, the adjudication determination itself may serve as a form of interim relief, providing rapid cash‑flow remedies while arbitration addresses the underlying dispute on its merits.

Step 6: Establish the Procedural Timetable, Exchange Documents and Manage Experts

Once the tribunal is constituted, a case‑management conference sets the procedural calendar. The tribunal will issue directions covering:

  • Pleadings, Statements of Claim and Defence, with or without a Reply
  • Document production, typically proportionate electronic disclosure, not full US‑style discovery
  • Expert evidence, whether party‑appointed or single joint experts, report exchange dates, and whether concurrent (“hot‑tub”) evidence will be used
  • Witness statements, fact‑witness statements filed in advance, with cross‑examination at hearing

Best practices at this stage include narrowing the issues through an agreed list of issues or a Scott schedule for defects claims, preparing an agreed facts bundle, and applying redactions only where genuine privilege or commercial sensitivity exists. Efficient document management at this point directly affects both cost and the tribunal’s ability to reach a well‑reasoned award.

Step 7: Attend the Hearing, Receive the Award and Take Post‑Award Steps

Hearings may be in person, virtual or hybrid. The tribunal hears opening submissions, examines witnesses and experts under oath, receives exhibits and closing arguments. In smaller construction disputes, a hearing of one to three days is common; complex multi‑party cases may require ten or more hearing days.

After the hearing, the tribunal deliberates and issues its award. Award types include final awards, partial awards (deciding liability before quantum, for instance) and interim awards on discrete issues. Institutional rules typically allow 30–90 days for the tribunal to deliver a reasoned award, though extensions are possible by agreement or tribunal direction. The award will allocate costs, the tribunal has discretion, but a contractual costs provision will usually prevail.

Post‑award steps include applying for correction of clerical errors, requesting an additional award on claims presented but not dealt with, or commencing court proceedings to set aside the award on the narrow grounds permitted under the applicable arbitration statute. Enforcement of a Canadian arbitral award is obtained by filing it with the superior court of the province in which enforcement is sought.

Arbitration Timeline Summary

Step Who Does It Typical Duration (Estimate)
Review contract and gather evidence Claimant + counsel 3–14 days
Serve Notice of Dispute / Notice of Arbitration Claimant Immediately to 7 days after internal notice requirement
File with institution and pay initial fees Claimant 1–7 days (depends on institution)
Appointment of tribunal Parties / Institution 14–60 days (expedited possible)
Case management and document exchange Tribunal / Parties 30–120 days (varies with complexity)
Interim measures (if needed) Court or Emergency Arbitrator Days to weeks
Hearing Parties / Tribunal 1–10 days (longer for complex claims)
Award issued Tribunal 30–90 days after hearing (varies)

Documents Needed for Construction Arbitration

Assembling a complete documentary record at the outset saves time, reduces costs and strengthens the claim or defence. The following checklist covers the documents most frequently required. Retain originals or certified copies and maintain a clear chain of custody, gaps in the record can undermine credibility before the tribunal.

Document Notes
Construction contract + all amendments and addenda Include signed subcontract packages. Identify the arbitration clause, notice clauses and governing‑law clause by number.
Notice of Dispute / Notice of Arbitration (filed copy) Issued by claimant. Keep proof of service (registered mail receipt, courier tracking, email read receipt or affidavit of service).
Invoices, pay applications and lien notices Include certified pay applications with dates and amounts. Retain originals or certified copies.
Change orders and approved variations Owner/contractor approvals, signatures or emails authorising scope changes.
Site diaries, daily reports, photographs and test results Time‑stamped and preserved in original digital format. Back up immediately upon dispute arising.
Subcontractor and supplier agreements and correspondence Prove work and supply flows. Include delivery dockets and inspection records.
Expert reports and CVs Identify whether party‑appointed or single joint expert. Include CVs, prior expert statements and scope of instructions.
Payment certificates and certificates of substantial completion Note issuing authority. Validate dates, these trigger lien and holdback timelines.
Bond documents (performance and payment bonds) Issuing bank or insurer contact details. Retain original bond numbers and policy documents.
Licences, permits and regulatory approvals Relevant where claims relate to delay caused by permitting or regulatory compliance issues.
Proof of pre‑arbitration resolution attempts Mediation notices, without‑prejudice correspondence or dispute‑board decisions (if the contract requires these steps before arbitration).

Commonly overlooked documents include subcontractor pay applications, internal meeting minutes, change‑order approval emails and certified payroll records. Parties should also preserve metadata and avoid altering electronic files, construction law terminology around e‑discovery obligations is evolving rapidly, and tribunals increasingly expect proportionate but genuine disclosure of electronic records.

Arbitration Timeline Canada, Key Deadlines

Deadlines in construction arbitration arise from three sources: the contract, the institutional rules and provincial statutes. Missing any of them can bar relief, limit remedies or shift the costs calculus against you. The table below summarises typical deadlines, verify each against the specific clause, rule or statute applicable to your project.

Action / Trigger Typical Deadline or Timeframe Notes
Serve contractual notice of dispute (if clause requires) 7–30 days (check clause) Failure to serve within the contractual window may bar the claim entirely.
File Request / Notice of Arbitration with institution File as soon as claimant decides to proceed Filing fees payable on submission.
Institutional initial administrative deposit On filing (per fee schedule) ICDR Canada, ADRIC and ICC each have different scales.
Appointment of arbitrator 14–60 days Expedited or emergency procedures can shorten this to days.
Emergency interim relief application As soon as immediate risk arises May be to court (conservatory measures) or emergency arbitrator.
Hearing date 1–6 months after document exchange Depends on complexity, number of witnesses and tribunal availability.
Award delivery 30–90 days after hearing Some rules allow extensions; parties can agree a different timeline.

Province‑Specific Notes for 2026

The arbitration timeline in Canada is now directly affected by prompt‑payment and adjudication legislation. In Ontario, amendments to the Construction Act effective 1 January 2026 have clarified payment timelines, holdback release triggers and the relationship between adjudication determinations and subsequent arbitration proceedings. In British Columbia, the Construction Prompt Payment Act (Bill 20), which received Royal Assent on 27 November 2025, introduces staged implementation of prompt‑payment obligations and a statutory adjudication mechanism.

The likely practical effect is that parties may need to commence or complete an adjudication before, or concurrently with, arbitration. Adjudication decisions are generally binding on an interim basis and can be enforced quickly, giving claimants a cash‑flow remedy while the arbitration addresses the full merits. Limitation periods for commencing arbitration vary by province and by the nature of the claim. Do not assume a single pan‑Canadian limitation period applies, verify the applicable statute with counsel.

Arbitration Costs Canada, Fees, Budgets and Tax Considerations

Understanding the cost structure before filing is critical for budgeting and for making an informed decision about whether to commence construction arbitration. Costs fall into four broad categories: institutional fees, arbitrator fees, legal fees and expert‑witness fees. Legal and expert fees typically represent the largest share.

Item Typical Amount (2026 Estimate) Notes / Source
ICDR Canada initial filing / admin fee CAD 1,900 – CAD 6,900 (scaled by claim amount) Per ICDR Canada Arbitration Fee Schedule. Amounts vary by claim band.
ADR Institute of Canada (administration / simplified procedures) CAD 350 (small claims) to several thousand Per ADRIC rules and fee guidance.
ICC Court administrative costs (international) USD 5,000+ (scaled by claim) ICC scales vary; seek a formal estimate from the ICC Secretariat or counsel.
Arbitrator fees CAD 1,000 – CAD 6,000+ per day Varies by experience, complexity and region. Deposits typically required.
Legal fees (party costs) CAD 25,000 – CAD 500,000+ Depends on complexity, geography and expert use. Often the largest cost.
Expert witness fees CAD 5,000 – CAD 100,000+ per expert Depends on discipline, report complexity and hearing‑time commitment.
Court interim‑measures filing fees Varies by province and type of application Court costs are separate from arbitration institution fees.

These are illustrative estimates. Verify each figure against the relevant institution’s current fee schedule before committing.

Cost Allocation and Budgeting Tips

The tribunal has broad discretion to allocate costs in the award. A contractual costs provision, for example, “costs follow the event”, will usually prevail. Practical budgeting strategies include: requesting a fee cap or phased deposit schedule from the institution; staging expert work so that preliminary opinions precede full reports; and agreeing with the other party on a streamlined document‑production protocol to reduce legal costs. GST/HST may apply to arbitrator fees and institutional charges; consult tax counsel for recovery or input‑tax‑credit implications.

What Changes in 2026, Prompt‑Payment, Adjudication and How to Commence Construction Arbitration

Two major 2026 developments reshape the landscape in which parties decide whether and when to commence construction arbitration in Canada.

Ontario, Construction Act Amendments (Effective 1 January 2026)

Ontario’s amendments clarify prompt‑payment timelines, streamline adjudication procedures and refine holdback‑release triggers. The likely practical effect for parties considering arbitration is twofold: first, an adjudication can deliver a binding interim payment determination far more quickly than arbitration; second, adjudication outcomes will often be placed before the arbitral tribunal as evidence of the parties’ rights on an interim basis. Parties must preserve their arbitration rights by serving any contractual notices within the required windows, even while pursuing adjudication.

British Columbia, Construction Prompt Payment Act (Bill 20)

BC’s Construction Prompt Payment Act, which received Royal Assent on 27 November 2025, introduces a statutory adjudication mechanism with staged implementation. Early indications suggest that other provinces, notably Alberta, are progressing similar regimes. The interaction between these processes and arbitration rights is critical: initiating adjudication first may provide immediate cash‑flow relief, but failure to follow required prompt‑payment timelines may prejudice downstream remedies.

Tactical Checklist for 2026

  • Serve a contractual notice of dispute within the required window, even if adjudication is your first step.
  • Calendar all prompt‑payment response deadlines so that arbitration limitation periods are not inadvertently missed.
  • Document adjudication timelines, determinations and enforcement steps, these form part of the arbitration record.
  • Consider seeking interim court relief where adjudication remedies are insufficient to protect security or project works.

Common Pitfalls and How to Avoid Them

  • Failing to serve required contractual notices. Many contracts impose strict notice requirements as conditions precedent to arbitration. Missing these can extinguish the right to arbitrate. Include a notice template and proof‑of‑service checklist in your dispute file from day one.
  • Ignoring prompt‑payment and adjudication timelines. Under the 2026 regimes in Ontario and BC, statutory payment and adjudication deadlines run in parallel with arbitration rights. Calendar every critical date and engage counsel to coordinate both tracks.
  • Poor evidence preservation. Site diaries, photographs and daily reports are frequently lost, overwritten or deleted after project completion. Implement immediate evidence‑capture and chain‑of‑custody protocols the moment a dispute arises.
  • Selecting an arbitrator without construction expertise. A tribunal that lacks technical knowledge of construction processes, standards and quantum methods will struggle with expert evidence. Shortlist candidates by both legal and technical experience, request CVs and check prior construction awards.
  • Underbudgeting for experts and legal fees. Arbitration costs Canada‑wide are dominated by professional fees, not institutional charges. Use staged costing, obtain fee estimates from experts before engagement and agree a cost‑management protocol with counsel at the outset.

Immediate Action Checklist

Once a dispute arises, take these five steps without delay:

  1. Locate the contract and read the arbitration clause in full.
  2. Secure and back up all project records, electronic and hard copy.
  3. Preserve lien and holdback rights under the applicable provincial Construction Act.
  4. Engage construction‑law counsel to assess whether adjudication, arbitration or both should proceed.
  5. Prepare a preliminary budget covering institutional fees, arbitrator fees, legal costs and expert fees.

Conclusion

Knowing how to commence construction arbitration in Canada, and doing so correctly, can determine the outcome of a multi‑million‑dollar dispute. The process is sequential and deadline‑driven: confirm your contractual right to arbitrate, serve proper notices, file with the institution, appoint a qualified tribunal, manage documents and experts efficiently, and prepare rigorously for the hearing. The 2026 prompt‑payment and adjudication amendments in Ontario, British Columbia and other provinces add a new layer of complexity, requiring parties to coordinate statutory adjudication timelines with arbitration rights. Use the checklists, timeline table and cost estimates in this guide as a starting framework, verify each figure and deadline against the applicable rules and statutes, and seek specialist construction‑law counsel early.

A searchable lawyer directory can help you identify qualified practitioners in your jurisdiction.

Need Legal Advice?

This article was produced by Global Law Experts. For specialist advice on this topic, contact Brendan D. Bowles at Glaholt Bowles LLP, a member of the Global Law Experts network.

Sources

  1. Department of Justice Canada, Commercial Arbitration Act (Consolidated)
  2. Ontario Bar Association, Ontario’s Construction Act: Key 2026 Amendments and Practical Implications
  3. Fasken, Ontario’s Amendments to the Construction Act Take Effect January 1, 2026
  4. British Columbia Government, Prompt Payment in the Construction Industry
  5. ADR Institute of Canada, Arbitration Rules & Codes
  6. ICDR Canada, Arbitration Fee Schedule
  7. AAA / ICDR, International Fee Schedule
  8. ADR Institute of Canada, Construction Adjudication Program
  9. UNCITRAL, Model Law on International Commercial Arbitration

FAQs

How much does construction arbitration cost?
Costs depend on the institution, the claim amount, arbitrator fees, legal representation and expert evidence. Institutional filing fees range from a few hundred dollars (ADRIC simplified track) to several thousand dollars (ICDR Canada, ICC). Legal and expert fees typically constitute the largest portion. See the costs table above for 2026 estimates and verify with the chosen institution’s current fee schedule.
There is no default “winner.” Outcomes depend on the contract terms, the quality of documentary evidence, the persuasiveness of expert reports and the tribunal’s assessment of credibility. A well‑prepared claimant with contemporaneous records and clear contractual entitlements improves its prospects significantly. See the section on preparation for and conduct of arbitration hearings for further guidance.
Under the federal Commercial Arbitration Act and provincial equivalents, certain public‑law and constitutional matters, specific insolvency proceedings and some statutory lien‑enforcement steps cannot be referred to arbitration. Always verify the scope of the arbitration clause against the applicable statute before filing.
Canadian law does not require arbitrators to be lawyers. Parties may appoint engineers, quantity surveyors or other construction professionals, either alone or alongside a legally qualified chair. Appointment follows the mechanism in the contract and the institutional rules, party nomination, institutional selection from a panel, or a combination. The ADR Institute of Canada Arbitration Rules set out a detailed appointment protocol.
Yes. International parties can arbitrate in Canada provided the seat is in a Canadian province and the arbitration clause or a subsequent agreement so provides. Canada has adopted the UNCITRAL Model Law on International Commercial Arbitration in both federal and most provincial statutes, facilitating recognition and enforcement of international awards.
Missing a notice or filing deadline can bar relief or significantly limit available remedies. In narrow cases, a court may grant relief from forfeiture or extend time, but this is discretionary and uncertain. The safest approach is to engage counsel immediately upon becoming aware of the dispute and to calendar every deadline from the outset.
Engage construction‑law counsel before serving any notice or filing. Early legal involvement ensures that notices are correctly drafted, limitation periods are preserved, evidence is secured, interim relief options are assessed and an expert budget is prepared. Delaying legal engagement frequently increases costs and reduces strategic options.

Find the right Legal Expert for your business

The premier guide to leading legal professionals throughout the world

Specialism
Country
Practice Area
LAWYERS RECOGNIZED
0
EVALUATIONS OF LAWYERS BY THEIR PEERS
0 m+
PRACTICE AREAS
0
COUNTRIES AROUND THE WORLD
0
Join
who are already getting the benefits
0

Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.

Naturally you can unsubscribe at any time.

About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Global Law Experts App

Now Available on the App & Google Play Stores.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Contact Us

Stay Informed

Join Mailing List
About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Global Law Experts App

Now Available on the App & Google Play Stores.

Contact Us

Stay Informed

GLE

Lawyer Profile Page - Lead Capture
GLE-Logo-White
Lawyer Profile Page - Lead Capture

How to Commence Construction Arbitration in Canada (step‑by‑step, 2026 Update)

Send welcome message

Custom Message