Our Expert in Denmark
No results available
Understanding how to start construction arbitration in Denmark is essential for any contractor, subcontractor or project owner facing a dispute under a Danish construction contract. The vast majority of Danish construction agreements, including the widely used AB 18, ABT 18 and ABR 18 standard forms, channel disputes away from the ordinary courts and toward arbitration administered by the Danish Building and Construction Arbitration Board (Voldgiftsnævnet for Bygge- og Anlægsvirksomhed) or, for non-construction-specific commercial disputes, the Danish Institute of Arbitration (DIA). This guide sets out, in practical sequential order, every action a claimant must take, from reviewing the arbitration clause through to obtaining an enforceable award, and provides checklists for required documents, indicative timelines, cost categories and common pitfalls to avoid.
Arbitration in Denmark is governed by the Danish Arbitration Act (Voldgiftsloven), which is closely modelled on the UNCITRAL Model Law on International Commercial Arbitration. In the construction sector, arbitration is the default dispute-resolution mechanism rather than litigation. This is because the AB 18 family of standard-form contracts expressly requires arbitration for disputes that cannot be resolved by negotiation or mediation.
Arbitration is used whenever the underlying contract contains a valid arbitration clause, and in Danish construction practice, nearly all professionally drafted contracts do. The AB 18 (general conditions for building and construction works), ABT 18 (design-and-build) and ABR 18 (consulting services) each include dispute-resolution provisions that direct the parties first to negotiation and, failing that, to arbitration. For projects that do not use the AB 18 suite, parties may agree on ad hoc arbitration or choose institutional rules such as those of the DIA.
Most construction arbitrations in Denmark are institutional, administered by the Arbitration Board under its own procedural rules, which were updated in 2019 to align with the AB 18 contracts. The DIA offers a parallel set of rules for commercial disputes, including a simplified arbitration procedure suited to lower-value claims. Ad hoc arbitration, where the parties design the procedure themselves, usually with reference to the Danish Arbitration Act, is less common in construction but remains available if the contract so provides. The choice between institutional and ad hoc arbitration affects filing requirements, fee structures and tribunal-appointment mechanics, all of which are addressed below.
Before initiating arbitration, a prospective claimant must confirm that every eligibility requirement and contractual pre-condition is met. Failing to do so can result in jurisdictional objections, delays or even dismissal of the claim.
The starting point is the contract itself. The claimant must locate the dispute-resolution clause (typically found in the general conditions or a separate appendix) and verify the following: the identity of the administering institution, the seat of arbitration, the applicable procedural rules, the number of arbitrators, the language of proceedings, and any requirements for prior negotiation or mediation. Under the Danish Arbitration Act, arbitration can be agreed for all civil-law matters over which the parties have free disposal. If the clause is ambiguous or pathological, for example, referring to a non-existent institution, specialist legal advice should be sought before filing.
AB 18 and its companion forms impose mandatory pre-arbitration steps. These typically include written notice of the dispute to the opposing party, an invitation to negotiate and, in certain cases, referral to mediation or a dispute-resolution board. If the contract requires mediation before arbitration, a claimant who bypasses that step risks having the arbitration stayed until the requirement is satisfied. It is therefore critical to document every escalation step in writing, with proof of delivery, before preparing the Notice of Arbitration.
Any party to the arbitration agreement may commence arbitration. Subcontractors who have a direct contractual relationship with the main contractor (and whose subcontract contains its own arbitration clause) may bring claims under that subcontract. Where assignment of rights has occurred, the assignee must present evidence of valid assignment. Foreign companies are equally entitled to initiate arbitration seated in Denmark, provided they satisfy any requirements for local representation or power of attorney.
The following numbered steps map the entire initiation sequence for a construction arbitration in Denmark. The table below summarises the key actors and indicative durations; the detailed guidance follows.
| Step | Who does it | Typical duration |
|---|---|---|
| 1. Contract check and pre-notice actions | Claimant (in-house counsel / contractor) | 1–7 days |
| 2. Draft and serve Notice of Arbitration | Claimant | 3–14 days to prepare |
| 3. File case with institution | Claimant | Filing acknowledgement within 1–7 days |
| 4. Respondent files Answer | Respondent | 14–28 days after service |
| 5. Appointment of tribunal and preliminary conference | Institution / Parties / Tribunal | 2–8 weeks |
| 6. Document exchange and evidence phase | Parties | 4–12 weeks |
| 7. Hearing(s) | Tribunal and parties | 1 day to 2+ weeks |
| 8. Award issued | Tribunal | 1–8 weeks after closing submissions |
Note: all durations are indicative and depend on claim complexity, the institution’s procedural rules and any contractual deadlines under AB 18. Parties should verify exact time limits with the applicable rules.
Begin by obtaining a complete copy of the signed contract, including all appendices, amendments and change orders. Identify the dispute-resolution clause and confirm the arbitration institution, seat, number of arbitrators, language and governing law. Check whether the clause requires prior negotiation, mediation or referral to a dispute-resolution board. Verify that any contractual notice periods (for example, time bars for raising defect claims) have been observed. This internal review should also flag whether the dispute falls within the scope of the arbitration agreement, disputes concerning personal injury, for instance, are typically excluded.
The Notice of Arbitration (sometimes called the Request for Arbitration or Statement of Claim) is the formal document that triggers the arbitration. It should contain, at minimum:
Service must comply with the method prescribed in the contract or the institution’s rules. In practice, most Notices are served by courier or registered mail to the respondent’s registered address, with a copy filed simultaneously with the institution. Retain proof of service, a courier receipt or postal confirmation, as evidence of the date on which the arbitration was commenced.
Once the Notice of Arbitration has been served on the respondent, the claimant files a copy with the administering institution together with the required registration fee. For a Danish Institute of Arbitration filing, the claimant submits the Notice, supporting exhibits, proof of service on the respondent and payment of the administrative fee. The DIA will acknowledge receipt and review the filing for formal completeness. If the arbitration is conducted under the Danish Building and Construction Arbitration Board’s rules, the filing procedure follows that Board’s own requirements, which are published on its official website. For ad hoc arbitration, there is no institutional filing step; instead, the parties must agree on the procedure for appointing the tribunal.
Under most institutional rules, the respondent has a defined period, typically 14 to 28 days from receipt of the Notice, to file an Answer. The Answer should address each of the claimant’s factual and legal assertions and, if applicable, include any counterclaims. If the respondent fails to file an Answer within the prescribed period, the arbitration generally proceeds on the basis of the claimant’s submissions. The institution will then facilitate the appointment of the tribunal. Depending on the rules and the contract clause, this may involve each party nominating one arbitrator and the two party-nominated arbitrators selecting a chairperson, or the institution may appoint the entire tribunal.
Once constituted, the tribunal convenes a preliminary procedural conference to set the timetable for submissions, evidence and hearings.
If the claimant needs urgent protection, for example, an order to preserve evidence on a construction site, a freezing order over the respondent’s assets, or an injunction to prevent disposal of disputed property, it may apply for interim measures. Under the Danish Arbitration Act, an arbitral tribunal has the power to grant interim measures once it is constituted. Before the tribunal is appointed, or where the measure requires enforcement by a court, the claimant may apply directly to the Danish district courts. Applying for interim relief does not waive the right to arbitrate; the Danish Arbitration Act expressly preserves the arbitration agreement in these circumstances.
Following the preliminary conference, the parties exchange documents, witness statements and expert reports in accordance with the timetable set by the tribunal. In Danish construction arbitrations, documentary evidence is paramount: contracts, correspondence, site diaries, inspection records, payment certificates and variation orders form the core of most cases. Witness statements should be signed, short and factual. Expert evidence, whether on technical defects, delay analysis or quantum, is often determinative. Parties should ensure that expert reports clearly state the expert’s qualifications, instructions received and assumptions made. The revised rules on taking evidence in arbitration proceedings seated in Denmark, which build on established Danish procedural principles, provide additional guidance on document production and privilege.
The hearing is conducted before the tribunal at the agreed venue, typically in Copenhagen. Both parties present their cases through opening submissions, witness examination and closing arguments. Hearings in construction disputes can last from a single day (for straightforward payment claims) to several weeks (for complex defects or delay disputes involving multiple experts). After the hearing and any post-hearing submissions, the tribunal deliberates and issues its award. The award is final and binding, with no right of appeal on the merits under the Danish Arbitration Act. An award can be enforced in Denmark through the district courts and internationally under the New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards.
Assembling the right documents at the outset avoids delays and strengthens the claimant’s position. The following checklist covers the core documents required when initiating arbitration under AB 18 or DIA rules.
| Document | Notes |
|---|---|
| Notice of Arbitration / Claim (signed) | Include contract reference, clause number, relief sought, amount and remedy. Signed by authorised representative. |
| Contract(s) and appended AB 18 / ABT / ABR | Full signed contract(s) with amendments and signed change orders. |
| Final account / payment records / invoices | Outstanding sums, payment dates, payment terms and bank confirmations. |
| Correspondence and prior dispute notices | All letters and emails evidencing contractual notice steps, with delivery proof. |
| Technical reports and inspection records | Site diaries, defects reports, photographs, materials tests. Identify author and date. |
| Drawings, specifications and bill of quantities | As-built vs contract documents with version dates. |
| Subcontractor agreements and warranties | If claimant is a subcontractor, show contractual privity or valid assignment. |
| Witness statements (signed) | Short, factual statements with the witness’s CV and defined scope. |
| Expert reports (commercial / technical) | State scope, qualifications, instructions and assumptions. Attach expert CV. |
| Power of attorney / authorisation | Board resolution or POA showing signatory authority. Provide Danish and English versions if needed. |
| Evidence of service / filing receipts | Courier receipts or postal confirmations proving service on the respondent and filing with the institution. |
| Translations / certified copies | If originals are not in the language of the proceedings, provide certified translations. |
Organise documents in a numbered exhibits index and maintain both electronic and hard-copy sets. Early assembly of this file shortens the drafting period for the Notice of Arbitration and reduces the risk of omitting critical evidence.
The total duration of a construction arbitration in Denmark depends on the complexity of the dispute, the number of parties and the responsiveness of the tribunal and institution. Industry observers expect a straightforward payment dispute to reach an award within six to nine months of filing, while complex multi-party defects or delay cases may take 12 to 24 months or longer.
Key deadlines to calendar include:
Exact deadlines vary by contract and institution. Parties should verify each deadline against the applicable AB 18 clause and the rules of the chosen institution before committing to a procedural timetable.
Understanding the cost structure is essential for budgeting and for managing commercial expectations. The principal categories of arbitration costs in Denmark are set out below.
| Cost item | Typical basis | Notes |
|---|---|---|
| Institution filing / registration fee | Fixed or scaled by claim value | Payable on filing. Check the current fee schedule published by the relevant institution. |
| Arbitrator fees | Hourly, daily or fixed per case | Depends on tribunal size, arbitrator experience and estimated hearing days. |
| Legal fees (counsel) | Hourly or fixed / capped | Varies by firm and complexity. Discuss fee arrangements and cost recovery prospects at the outset. |
| Expert fees | Hourly or per report | Technical and quantum experts. Often a significant portion of total cost in construction disputes. |
| Hearing venue, transcription, travel | Variable | Hearings typically take place in Copenhagen. Include travel and accommodation for witnesses. |
| Security for costs | Case dependent | The tribunal or Danish courts may order security for costs in appropriate circumstances. |
In Danish arbitration practice, the tribunal has broad discretion to allocate costs in the final award. The likely practical effect is that the losing party bears a significant share of the arbitration costs, including a contribution to the prevailing party’s legal fees, although full indemnity is not always awarded. Parties should factor in the possibility that cost recovery may be partial and plan their litigation budget accordingly. The applicable institution’s fee schedule should be consulted directly for current figures.
At the time of this review, no new Danish arbitration statute has been enacted that alters the fundamental steps for initiating construction arbitration in Denmark. The Danish Arbitration Act (Voldgiftsloven) and the AB 18 standard forms remain the governing instruments.
Parties preparing to file in 2026 should verify the following before proceeding:
Avoiding procedural errors at the outset can save months of delay and significant cost. The following pitfalls are encountered regularly in Danish construction arbitrations.
This article was produced by Global Law Experts. For specialist advice on this topic, contact Christian Johansen at Bruun & Hjejle, a member of the Global Law Experts network.
posted 42 minutes ago
posted 56 minutes ago
posted 1 hour ago
posted 1 hour ago
posted 2 hours ago
posted 2 hours ago
posted 2 hours ago
posted 2 hours ago
posted 2 hours ago
posted 3 hours ago
posted 3 hours ago
posted 3 hours ago
No results available
Find the right Legal Expert for your business
Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.
Naturally you can unsubscribe at any time.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Send welcome message