[codicts-css-switcher id=”346″]

Global Law Experts Logo
termination clause in construction contract

Termination Clause in Construction Contract, France: Notices, Cure Periods & Article 1225

By Global Law Experts
– posted 2 hours ago

Every termination clause in a construction contract governed by French law must satisfy the procedural safeguards set out in Article 1225 of the Civil Code, most critically, the obligation to serve a formal written notice (mise en demeure) and to grant the defaulting party a reasonable period to cure its breach before the contract can be brought to an end. These requirements, introduced by the 2016 reform of French contract law and now firmly embedded in construction-sector practice, apply to employers, general contractors and subcontractors alike.

This guide explains the legal framework, walks through the notice and cure workflow step by step, compares suspension with termination, addresses financial consequences such as payment after termination of a construction contract, and provides annotated model clause language and sample notices that can be adapted for immediate use.

Quick Summary, Key Practical Rules

  • Article 1225 mandate. A contractual termination clause (clause résolutoire) is only enforceable if the terminating party has first served a mise en demeure that identifies the breach, demands performance and fixes a reasonable cure period. The clause must also specify the breaches that trigger termination.
  • Notice mechanics. French courts expect the mise en demeure to be sent by registered letter with acknowledgement of receipt (lettre recommandée avec accusé de réception, or “LRAR”) or served by a judicial officer (commissaire de justice, formerly huissier). Informal emails or verbal warnings do not satisfy the statutory requirement.
  • Cure period. There is no fixed statutory cure period. The period must be “reasonable” in light of the nature of the obligation, the scale of the works and any contractual stipulations. Industry observers generally consider 15 to 30 days appropriate for most construction breaches, though shorter periods may be justified for health-and-safety failures.
  • Immediate action. If you are drafting or reviewing a termination clause in a construction contract under French law, verify that the clause expressly lists the triggering events, prescribes the service method, sets a cure period aligned with Article 1225, and addresses payment, demobilisation and final-account mechanics.

Legal Framework, Article 1225, Civil Code and Core Principles

Text and translation of Article 1225

Article 1225 of the French Civil Code, as enacted by Ordinance No. 2016-131 of 10 February 2016 and subsequently ratified, governs contractual termination clauses (clauses résolutoires). The provision states that such a clause must specify the commitments whose non-performance will trigger termination, and that termination is subject to a prior mise en demeure that has remained without effect. The official English translation published by the French Ministry of Justice renders the key sentence as: “Termination is subject to a prior formal notice which has not been complied with, mentioning expressly the termination clause.

” This translation confirms two mandatory preconditions: first, the formal notice must cite the termination clause itself; second, the debtor must be given the opportunity to perform before termination takes effect.

In construction practice, Article 1225 means that no termination clause in a construction contract, however clearly it describes the triggering events, can operate automatically without the notice-and-cure sequence. A clause that purports to terminate “immediately and without prior notice” (de plein droit et sans mise en demeure préalable) is unenforceable to the extent it dispenses with the formal notice requirement.

How courts interpret “reasonable”

The Civil Code does not define the length of a “reasonable” cure period. French courts, including the Cour de cassation, assess reasonableness on a case-by-case basis, considering the complexity of the breach, the time realistically needed to mobilise resources, weather conditions affecting construction schedules, and whether the defaulting party had already been warned informally. Early indications from post-2016 case law suggest that cure periods shorter than eight days are at high risk of being struck down for construction-related obligations, while periods of 15 to 30 days are routinely upheld. Good-faith behaviour by both parties (bonne foi, Article 1104 of the Civil Code) colours the entire assessment.

Grounds for Termination in Construction Contracts

Terminating a construction contract under French law can be grounded in contractual provisions, statutory rights or, in some cases, both simultaneously. The key distinction is between termination for cause (résiliation pour faute) and termination for convenience (résiliation pour convenance).

Five major ways a construction contract can end

  • Mutual termination (résiliation amiable). The parties agree in writing to bring the contract to an end, typically settling outstanding accounts and demobilisation costs at the same time.
  • Termination for cause (résiliation pour faute). One party invokes a material breach, persistent delay, defective work, abandonment of site, or non-payment, following the Article 1225 notice-and-cure process.
  • Termination for convenience (résiliation pour convenance). The employer exercises a unilateral right, often expressly included in French standard-form construction contracts (such as the CCAG-Travaux for public works), to terminate without fault. Compensation is typically owed for work performed and lost profit.
  • Frustration or force majeure (Article 1218). Performance becomes permanently impossible due to an event beyond the parties’ control, a natural disaster destroying the site, for instance. If only temporary, force majeure suspends performance rather than terminating the contract outright.
  • Expiry or completion. The contract ends naturally upon provisional acceptance (réception provisoire) or final acceptance (réception définitive) of the works, or upon the contractual expiry date.

Contractor vs employer, when can each party terminate?

Party Common contractual grounds Typical evidence required
Employer / Client Persistent delay exceeding contractual tolerance; defective workmanship not corrected after notice; abandonment of site; contractor insolvency (subject to safeguard/restructuring rules); failure to maintain required insurance Site inspection reports; programme updates showing delay; correspondence demonstrating non-compliance after cure notice; evidence of insolvency proceedings
Contractor Prolonged non-payment after invoice due dates; failure by employer to provide site access or permits; employer-ordered suspension exceeding agreed period; employer insolvency Unpaid invoices with proof of service; correspondence requesting access; records of suspension duration; published insolvency notice

When can a contractor terminate the contract? In practice, contractors more often suspend performance as a first step and escalate to termination only after a cure notice has gone unanswered. Contractual drafting should address this escalation path explicitly.

Notice and Cure Mechanics, Step-by-Step Compliance with Article 1225

Compliance with the termination clause in a construction contract under French law depends on executing the notice-and-cure sequence correctly. The workflow below sets out the practical steps.

Step-by-step workflow

  1. Identify the triggering breach. Review the contractual termination clause and confirm that the default falls within one of the expressly listed triggering events. Article 1225 only protects clauses that “specify the commitments” whose breach activates termination.
  2. Draft the mise en demeure. The formal notice must (a) describe the breach in factual terms, (b) cite the relevant contractual clause and Article 1225 of the Civil Code, (c) require the defaulting party to remedy the breach within a stated period, and (d) state expressly that failure to comply will result in termination.
  3. Choose the service method. Send the notice by LRAR (registered letter with acknowledgement of receipt) to the address stipulated in the contract, or instruct a commissaire de justice to serve it directly. Where the contract requires a specific service method, follow it precisely, deviation may invalidate the notice.
  4. Calculate the cure period. Set a period that is reasonable in the circumstances. For programme-related breaches (delay, failure to mobilise), 15 to 30 days is typical. For payment defaults, some contracts specify 14 days. For safety-critical breaches where people or property are at immediate risk, a shorter period, or, exceptionally, no cure period, may be justified.
  5. Monitor and document. Record whether the acknowledgement of receipt was returned, track the expiry date of the cure period, and document any remedial steps (or lack of steps) taken by the defaulting party.
  6. Serve the termination notice. If the cure period expires without adequate performance, serve a second notice confirming that the termination clause is now activated. This notice should reference the original mise en demeure, state that the cure period has expired without remedy, and declare the contract terminated with effect from the date of the notice (or such later date as the clause prescribes).

Emergency exceptions

In cases of sufficiently grave breach, for example, a contractor’s total abandonment of works or an imminent safety hazard, French law allows the creditor to terminate without affording a cure period, provided the gravity of the breach justifies immediate action (Article 1226 of the Civil Code). However, the burden of proof falls squarely on the terminating party. Industry observers expect courts to scrutinise such “emergency” terminations rigorously, particularly in high-value construction disputes, and to award damages if the urgency was not genuinely justified.

Sample mise en demeure (cure notice)

Note: This is a template only. It must be adapted to the facts and reviewed by French counsel before use.

“[Company name and address of terminating party] To: [Company name and address of defaulting party] Date: [Date] Subject: Mise en demeure, Contract [reference number] dated [date] Dear [Name], We hereby give you formal notice, in accordance with Article 1225 of the Civil Code and Clause [X] of the Contract, to remedy the following breach: [describe the breach in factual terms, e. g. , ‘failure to achieve the Milestone 3 completion date of [date], the works being more than [X] days behind the contractual programme’]. You are required to remedy this breach within [15/30] calendar days from the date of receipt of this letter.

Should you fail to do so, we reserve the right to terminate the Contract in accordance with Clause [X], without further notice.

Suspension vs Termination of Contract, Comparison and Consequences

Suspension and termination of a contract are frequently confused in construction practice, yet they carry fundamentally different legal consequences. The table below clarifies the key distinctions relevant to French construction law.

Criterion Suspension Termination
Typical triggers Non-payment by employer; dangerous site conditions; temporary impossibility; employer-ordered pause Material breach after cure period expires; contractor insolvency; abandonment; explicit contractual triggers
Effect on the contract Contract remains in force; performance obligations are paused; time extensions may apply Contract ends permanently; future obligations cease; rights to damages and final accounting arise
Common remedies Interest on late payment; claim for standby/delay costs; right to resume or escalate to termination Damages for breach; completion by replacement contractor at defaulting party’s cost; retention release; final-account settlement

In French construction practice, a contractor facing non-payment will typically suspend works first, giving the employer a further opportunity to pay, before escalating to formal termination. The suspension itself must comply with good-faith obligations and, where the contract requires it, with a notice procedure. A poorly executed suspension can expose the contractor to counter-claims for wrongful abandonment, so adherence to the contractual sequence is essential.

Financial Consequences, Payment, LDs, Demobilisation and Final Accounting

Understanding what happens to payment after termination of a construction contract is one of the most commercially significant issues for both parties. French law and standard construction contracts typically address the following areas.

  • Payment for work performed. The contractor is generally entitled to payment for all work properly executed and accepted up to the date of termination, regardless of which party terminated. This entitlement survives termination because it relates to obligations already performed.
  • Demobilisation costs. Where the employer terminates for convenience, the contractor can claim demobilisation costs, expenses incurred in removing equipment, releasing subcontractors and closing the site. For termination for cause, the breaching party may forfeit such claims, but the contract should address this expressly.
  • Liquidated damages (clause pénale). French law treats liquidated damages clauses as clauses pénales under Article 1231-5 of the Civil Code, giving courts the power to increase or reduce the stipulated amount if it is “manifestly excessive or derisory.” In construction disputes, courts frequently exercise this power, particularly where the employer’s actual loss is disproportionate to the contractual penalty.
  • Set-off (compensation). The employer may set off damages for delay or defects against sums otherwise owed to the contractor, provided the set-off conditions under Articles 1347 to 1348-2 of the Civil Code are met, notably, that the debts are certain, liquid and due.
  • Completion costs. Where termination follows the contractor’s default, the employer may engage a replacement contractor to complete the works and claim the additional cost from the defaulting contractor. Accurate records, including tender comparisons, site surveys and interim accounts, are critical to substantiating these claims.
  • Subcontractor treatment. Under the French subcontracting law (loi du 31 décembre 1975), approved subcontractors benefit from a direct-payment right (action directe) against the employer. Termination of the main contract does not automatically extinguish subcontractor claims, and employers must account for subcontractor entitlements in the final settlement.
  • Retention and warranties. Retention sums are released according to the contractual schedule (typically at réception or at the end of the guarantee period). Termination does not accelerate release unless the parties agree otherwise.

Drafting the Termination Clause, Recommended Language and Red Flags

A well-drafted termination clause in a construction contract governed by French law should cover four core elements: triggering events, notice and cure mechanics, service method, and financial consequences. Below is an annotated model structure, followed by a red-flag checklist.

Model clause structure (annotated)

  • Clause A, Termination for cause. “Either Party may terminate this Contract by notice if the other Party commits a material breach of any of the following obligations: [list specific obligations, programme compliance, payment within [X] days, insurance maintenance, health-and-safety compliance]. The terminating Party shall first serve a mise en demeure by LRAR or commissaire de justice, identifying the breach and granting a cure period of not less than [15/30] calendar days. If the breach is not remedied within the cure period, the terminating Party may serve a termination notice taking effect [X] days after receipt.” This tracks Article 1225 by specifying the triggering commitments and mandating the notice-and-cure sequence.
  • Clause B, Termination for convenience (employer only). “The Employer may terminate this Contract for convenience upon [30] calendar days’ written notice. The Contractor shall be entitled to payment for work performed, demobilisation costs and a reasonable margin on uncompleted works, as agreed or determined in accordance with Clause [X].” This provides certainty for both parties and avoids disputes over the contractor’s lost-profit entitlement.
  • Clause C, Post-termination obligations. “Upon termination, the Contractor shall vacate the site within [X] days, deliver all as-built documents, and participate in a joint final-account survey. The Employer shall release retention sums in accordance with Clause [X] and settle the final account within [X] days of agreement or determination.”

Red-flag checklist

  • Automatic termination without cure. Clauses purporting to terminate “immediately and without prior notice” contravene Article 1225 and are unenforceable.
  • Ipso facto insolvency clauses. Clauses that terminate the contract solely because the other party enters insolvency proceedings may conflict with French insolvency law (Code de commerce, Book VI), which allows the court-appointed administrator to decide whether to continue or terminate ongoing contracts.
  • Vague triggering events. A clause that refers generically to “any breach” without specifying the commitments in question may fail the Article 1225 specificity requirement.
  • Unreasonably short cure periods. A cure period of fewer than eight days for non-urgent construction breaches carries a high risk of judicial challenge.
  • No payment or demobilisation mechanics. Omitting post-termination financial provisions creates ambiguity and prolongs disputes. Always include a final-account timetable.

Disputes, Remedies and Enforcement

When a termination is contested, the defaulting party will typically argue that the mise en demeure was defective, the cure period was unreasonably short, or the breach did not fall within the clause’s listed triggers. French courts (Tribunal judiciaire or Tribunal de commerce, depending on the parties’ status) can declare the termination wrongful (résiliation abusive) and award damages to the wrongly terminated party, potentially including lost profit on the remaining works.

Provisional measures are available. A party facing wrongful termination can apply for emergency relief (référé) to preserve the status quo, for example, an order preventing the employer from engaging a replacement contractor pending a full hearing. Conversely, an employer may seek a référé order to gain access to the site if the terminated contractor refuses to vacate.

Many French construction contracts include arbitration clauses designating the International Chamber of Commerce (ICC) or the Centre de Médiation et d’Arbitrage de Paris (CMAP). Where arbitration applies, the tribunal, rather than the state courts, will determine whether the termination was valid. French courts will enforce arbitral awards under the provisions of the Code of Civil Procedure (Articles 1442 et seq.).

Checklist and Sample Notices

Six-point compliance checklist

  1. Confirm the termination clause lists specific triggering events (Article 1225 requirement).
  2. Draft the mise en demeure citing the clause, describing the breach and setting a reasonable cure period.
  3. Send the mise en demeure by LRAR or commissaire de justice to the contractual address.
  4. Monitor the cure period and document any response or continued default.
  5. If the breach persists, serve the formal termination notice referencing the unanswered mise en demeure.
  6. Initiate the final-account process, address demobilisation and preserve evidence for potential disputes.

Sample termination notice (after cure period expiry)

Note: This is a template only. It must be adapted to the facts and reviewed by French counsel before use.

“[Company name and address of terminating party] To: [Company name and address of defaulting party] Date: [Date] Subject: Termination of Contract [reference number] dated [date] Dear [Name], We refer to our mise en demeure dated [date], received by you on [date of acknowledgement of receipt], requiring you to [describe the required remedy] within [X] calendar days. The cure period expired on [date] and the breach identified in our mise en demeure has not been remedied. Accordingly, we hereby terminate the Contract with immediate effect in accordance with Clause [X] and Article 1225 of the Civil Code. We request that you vacate the site within [X] days and participate in the joint final-account survey as required by Clause [X].

All rights and remedies are expressly reserved.

For a full glossary of terms used in construction contracts, see the construction law glossary. To find a French construction lawyer, visit the Global Law Experts lawyer directory and filter by jurisdiction and practice area.

Need Legal Advice?

This article was produced by Global Law Experts. For specialist advice on this topic, contact Shaparak Saleh at Three Crowns, a member of the Global Law Experts network.

Sources

  1. Legifrance, Code civil (Article 1225)
  2. French Ministry of Justice, English Translation of the Civil Code
  3. Pinsent Masons, Termination and Suspension of Construction Contracts (Out-Law Guide)
  4. Cabinet Bessis, Termination of Contract by Notification
  5. Cour de cassation, Selected Case Law
  6. Eversheds Sutherland, France Termination Options
  7. A&O Shearman, Is Your Contractual Notice Period Enforceable in France?
  8. Aceris Law, Termination of Construction Contracts
  9. Practical Law (Thomson Reuters), Termination of Contractor for Cause

FAQs

How do I terminate a construction contract in France?
In France, termination usually requires that the terminating party first serve a formal written notice (mise en demeure) requiring performance and setting a reasonable cure period. If the other party fails to perform within that cure period, the contract can be validly terminated under Article 1225 of the Civil Code.
Article 1225 governs contractual termination clauses (clauses résolutoires). It requires, except in urgent situations, that the creditor give the debtor formal notice to perform, fixing a reasonable period for performance, before the termination clause in a construction contract, or any other contract, can take effect.
Suspension temporarily pauses performance obligations while the contract remains in effect. Termination ends the contract permanently and triggers final remedies, including damages and completion costs. In French construction practice, suspension often precedes termination as part of an escalation sequence.
Yes. Contractors commonly suspend performance for non-payment and may terminate after serving a cure notice if payment is not forthcoming. The contractual steps and Article 1225 requirements must be followed to avoid wrongful-termination claims.
Payment obligations depend on the contract and the reason for termination. The terminating party generally owes sums for work properly performed and, in some cases, demobilisation costs. The non-breaching party may claim damages or completion costs, clear payment and settlement mechanics should be included in the termination clause.
If the terminating party failed to serve the required formal notice, gave an unreasonably short cure period, or terminated for reasons not covered by the clause, a French court may find the termination wrongful and award damages, potentially including lost profit on the remaining contract value.
Yes. This article provides two sample notices, a mise en demeure (cure notice) and a final termination notice, that can be adapted to the facts. They are templates only and should be reviewed by French counsel before use.

Find the right Legal Expert for your business

The premier guide to leading legal professionals throughout the world

Specialism
Country
Practice Area
LAWYERS RECOGNIZED
0
EVALUATIONS OF LAWYERS BY THEIR PEERS
0 m+
PRACTICE AREAS
0
COUNTRIES AROUND THE WORLD
0
Join
who are already getting the benefits
0

Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.

Naturally you can unsubscribe at any time.

About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Global Law Experts App

Now Available on the App & Google Play Stores.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Contact Us

Stay Informed

Join Mailing List
About Us

Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.

Social Posts
[wp_social_ninja id="50714" platform="instagram"]
[codicts-social-feeds platform="instagram" url="https://www.instagram.com/globallawexperts/" template="carousel" results_limit="10" header="false" column_count="1"]

See More:

Global Law Experts App

Now Available on the App & Google Play Stores.

Contact Us

Stay Informed

GLE

Lawyer Profile Page - Lead Capture
GLE-Logo-White
Lawyer Profile Page - Lead Capture

Termination Clause in Construction Contract, France: Notices, Cure Periods & Article 1225

Send welcome message

Custom Message