Our Expert in South Africa
No results available
Last updated: 06 May 2026
Alternative dispute resolution in South Africa entered a new era on 22 April 2025 when the Judge President of the Gauteng Division of the High Court issued a Directive on Mediation, making mediation a mandatory procedural step before a civil trial date can be allocated. For construction stakeholders, contractors, employers, project managers, claims consultants and adjudicators, the Directive and its accompanying Mediation Protocol introduce compliance obligations that sit alongside, and sometimes interact uncomfortably with, the ADR mechanisms embedded in standard-form contracts such as FIDIC, JBCC, NEC and GCC.
This guide explains the Directive’s scope and exceptions, walks through the Protocol’s procedural requirements, and provides contract-specific checklists and strategy notes to help practitioners maintain ADR compliance without forfeiting contractual rights or statutory time bars.
Alternative dispute resolution in South Africa encompasses any process by which parties resolve disputes outside full-blown court litigation. South Africa’s ADR landscape has been shaped by the Arbitration Act 42 of 1965, the growth of court-annexed mediation rules in the Magistrates’ Courts, and, most significantly for commercial parties, contractual ADR clauses in standard-form construction and engineering agreements. The Department of Justice has long promoted ADR through its national policy framework, positioning mediation and conciliation as mechanisms to improve access to justice and reduce the burden on overburdened court rolls.
The principal ADR methods available to South African parties include mediation (a facilitated, non-binding negotiation), arbitration (a private, binding adjudicative process), adjudication (a rapid interim-binding determination common in construction), expert determination (a binding expert opinion on technical matters), and conciliation (a more evaluative form of facilitated settlement, frequently used in labour disputes before the CCMA). Each method differs in formality, enforceability, cost and speed, and parties frequently deploy more than one mechanism sequentially or concurrently under their contracts.
Construction disputes in South Africa typically follow a tiered ADR pathway prescribed by the relevant standard-form contract. FIDIC contracts provide for Dispute Adjudication Boards (DABs) or Dispute Avoidance/Adjudication Boards (DAABs), followed by amicable settlement and then arbitration. JBCC agreements include contractual adjudication. NEC contracts mandate early warning procedures and adjudication. GCC contracts similarly provide for dispute referral mechanisms. All of these pre-date, and now co-exist with, the Gauteng court’s mandatory mediation requirement, creating a multi-layered ADR compliance environment for construction dispute resolution.
The Gauteng mediation directive, issued by the Judge President on 22 April 2025 and accompanied by a media statement from the judiciary, establishes mandatory mediation as a prerequisite to trial-date allocation in specified civil matters before the Gauteng Division of the High Court. The Directive draws its authority from the Judge President’s administrative powers to manage the court roll and promote access to justice. It does not amend legislation but operates as a binding practice direction within the Division.
The scope of the Directive captures civil trial matters, including commercial, contractual and construction disputes, that are enrolled for hearing in the Gauteng Division. Parties who have not attempted mediation, or who cannot demonstrate compliance with the accompanying Mediation Protocol, risk having their matters postponed or deprioritised in trial-date allocation. Industry observers expect this to have a particularly significant impact on the construction sector, where lengthy trials and substantial claim values have historically congested the roll. The practical effect is that construction dispute resolution in Gauteng now requires a mediation step even where the underlying contract already prescribes adjudication or arbitration.
The Directive recognises that mandatory mediation will not be appropriate in every case. Matters that may be exempted include those involving urgency, national security, certain constitutional issues, or disputes where mediation is manifestly inappropriate (for example, where interim interdict relief is sought). Parties seeking an exemption must formally apply to the court and record the basis for the exemption in a written submission. The likely practical effect will be that courts scrutinise exemption applications carefully, so parties should document the specific grounds with supporting evidence rather than relying on generic objections.
The Mediation Protocol for the Gauteng Division, published alongside the Directive on 22 April 2025, sets out the detailed procedural mechanics of court-annexed mediation. It governs the referral process, the mandatory exchange of documents, mediator selection, confidentiality, and the mechanism for reporting outcomes to the court. ADR compliance requires strict adherence to each step.
The Protocol contemplates both party-appointed and panel-appointed mediators. Where parties agree on a mediator, they may appoint any accredited mediator of their choice. Where they cannot agree, the court may appoint a mediator from an approved panel. The Protocol requires each party to prepare and exchange a mediation statement or position paper summarising the facts, issues and relief sought. These documents must be exchanged in advance of the mediation session to ensure productive engagement. Confidentiality provisions protect mediation communications from disclosure in subsequent litigation, subject to limited exceptions such as evidence of fraud or perjury.
| Process Step | Responsible Party | Timing |
|---|---|---|
| Serve notice of intention to mediate | Claimant / Applicant | As soon as practicable after close of pleadings |
| Respond to mediation notice and propose mediator | Respondent / Defendant | Within the period stipulated in the Protocol after receipt of notice |
| Agree on or apply for appointment of mediator | Both parties / Court | Within the period stipulated in the Protocol after exchange of proposals |
| Exchange mediation position papers | Both parties | Prior to the mediation session as prescribed by the mediator |
| Conduct mediation session | Both parties + Mediator | Date set by mediator within Protocol timeframe |
| File mediation compliance certificate with Registrar | Mediator / Parties | Within the period prescribed by the Protocol after conclusion of mediation |
| Apply for trial date allocation | Claimant / Applicant | After filing of compliance certificate |
Practitioners should prepare the following before initiating mediation under the Protocol:
Construction dispute resolution is where the Gauteng mediation directive creates the most complex compliance landscape. Standard-form construction contracts already prescribe multi-tiered ADR processes, and court-mandated mediation before litigation now adds another layer that must be carefully coordinated. The central risk is that parties, focused on complying with court mediation, may inadvertently allow contractual time bars to lapse, waive adjudication rights, or create inconsistent positions across concurrent ADR proceedings.
The interaction between contractual ADR and court mediation raises several critical questions. Does participation in court mediation constitute “amicable settlement” under FIDIC? Does a court mediation outcome affect the binding nature of an NEC adjudicator’s decision? Can a party commence JBCC adjudication while simultaneously engaging in court-mandated mediation? Early indications suggest that the Directive does not intend to override contractual ADR mechanisms, but the absence of explicit guidance on the interface means practitioners must manage the interaction proactively.
Under FIDIC 2017 contracts, disputes are first referred to a Dispute Avoidance/Adjudication Board (DAAB), and parties must attempt amicable settlement before proceeding to arbitration. The Gauteng Directive’s mandatory mediation may be treated as an additional procedural requirement between amicable settlement and any court application, but it does not replace the DAAB process. Practitioners should ensure that DAAB referral notices and time bars are preserved independently of the court mediation timetable. Where a DAAB decision has already been issued, the mediation position paper should annex and reference that decision without reopening its findings unless both parties consent.
JBCC agreements provide for contractual dispute notices and adjudication as primary ADR mechanisms. Court mediation under the Protocol does not preclude parallel adjudication, and industry observers expect that parties will increasingly appoint adjudicators early to obtain interim binding decisions on payment disputes while simultaneously engaging in court-mandated mediation for the broader dispute. The key risk flag is ensuring that contractual notice periods for JBCC claims are not treated as suspended during mediation, they almost certainly are not.
NEC contracts emphasise proactive dispute management through early warning notices and compensation event procedures. The NEC adjudication mechanism produces binding decisions unless and until revised by a tribunal. Court mediation complements NEC’s collaborative ethos but must not be used to circumvent or delay adjudication. Practitioners should issue early warning notices in parallel with mediation before litigation steps, and ensure that the mediation position paper addresses any outstanding compensation events without conceding the adjudicator’s jurisdiction.
Under the GCC (General Conditions of Contract for Construction Works), disputes regarding design defects, variations, and extensions of time follow a prescribed referral mechanism. Court mediation adds an additional layer that must be sequenced after the contractual dispute referral steps. The primary risk is that mediation delays may push parties past prescription periods or contractual cut-off dates for variation claims, making proactive timeline management essential.
| Contract Type | Immediate Actions on Receiving Mediation Directive | Risk Flags |
|---|---|---|
| FIDIC (1999 & 2017) | Preserve DAAB findings; issue or confirm amicable settlement notice; prepare mediation position paper annexing DAAB decision | Contractual time bars for amicable settlement and arbitration notice may run concurrently with mediation; do not treat mediation as tolling these periods |
| JBCC | Serve contractual dispute notice; appoint adjudicator if interim binding decision needed; prepare parallel mediation and adjudication submissions | Payment dispute time limits are strict; adjudication and mediation may produce inconsistent outcomes requiring careful management |
| NEC | Issue early warning notices; notify compensation events; confirm adjudication referral; prepare mediation statement consistent with NEC records | NEC adjudicator’s decision is binding unless revised by tribunal; mediation must not be used to re-litigate adjudicated matters without consent |
| GCC | Complete contractual dispute referral; document variation and extension claims; prepare mediation bundle with quantity surveyor’s assessment | Prescription periods and contractual cut-off dates may expire during mediation; track all deadlines independently |
Compliance with the Gauteng mediation directive requires systematic preparation across legal, commercial and technical workstreams. The following checklist provides a step-by-step framework for alternative dispute resolution in South Africa under the new mandatory mediation regime.
Understanding when arbitration is more appropriate than mediation, and vice versa, remains critical even under the mandatory mediation regime. The Directive does not eliminate the right to arbitrate; it introduces mediation as a prerequisite to trial, not as a substitute for contractual arbitration. Parties whose contracts contain arbitration clauses retain those rights and should preserve them carefully during the mediation process.
| Issue Type | Prefer Mediation | Prefer Arbitration |
|---|---|---|
| Quantum-only disputes (e.g., payment valuation) | High settlement probability; commercial compromise feasible | Only if parties are entrenched and need a binding valuation |
| Extension of time / delay claims | Useful for narrowing issues and agreeing factual matrix | Preferred when concurrent delay analysis requires expert determination |
| Interim relief (e.g., security of payment, injunction) | Mediation cannot grant binding interim relief | Essential, arbitration or court application required |
| Multi-party or sub-contractor disputes | Effective for package settlements and relationship preservation | Necessary where binding allocation of liability among multiple parties is required |
| Defects and technical performance disputes | Useful for agreed remediation plans | Preferred when formal expert evidence and cross-examination are needed |
When drafting or reviewing dispute resolution clauses in light of the Gauteng Directive, practitioners should include language that expressly preserves arbitration rights during mediation. A sample preservation clause might read: “Nothing in this mediation, including any statements made or positions adopted, shall constitute a waiver of either party’s right to refer the dispute to arbitration in accordance with Clause [X] of this Agreement.” This ensures that mediation before litigation does not inadvertently extinguish contractual arbitration rights.
The introduction of mandatory mediation creates both risk and opportunity for construction project stakeholders. From a risk-management perspective, the most immediate concern is the potential for mediation timelines to overlap with contractual time bars, prescription periods and performance security expiry dates. Early dispute budgeting, modelling mediation costs against likely litigation costs and settlement ranges, enables parties to approach mediation with realistic commercial parameters rather than treating it as a procedural formality.
Claims teams should package disputes for mediation in a way that maximises settlement probability: lead with the strongest claims, present clear quantum summaries, and identify trade-offs that create value for both sides. Where works are ongoing, consider whether suspension provisions under the contract may be triggered by the dispute and how mediation timing interacts with any suspension period.
Professional indemnity insurers and performance bond issuers should be notified of disputes subject to mandatory mediation, as mediation outcomes may affect coverage triggers and bond call-out timelines. Contractor all-risk policies may also require notification of disputes that could crystallise into claims, do not treat mediation as a reason to delay insurer notification.
The Gauteng Directive on Mediation represents the most significant shift in alternative dispute resolution in South Africa in recent years. For construction stakeholders, the message is clear: mandatory mediation is now a procedural reality in the Gauteng Division, and non-compliance carries tangible consequences in the form of delayed trial allocation and potential adverse cost orders. However, the Directive does not displace contractual ADR mechanisms, it adds to them, creating a layered compliance environment that demands careful coordination.
Practitioners should act immediately: audit outstanding disputes for Gauteng Division jurisdiction, reconcile contractual ADR timelines with the mediation protocol’s requirements, preserve all contractual time bars independently, and prepare concise mediation position papers that protect both settlement prospects and arbitration rights. Early engagement with accredited mediators and proactive claims packaging will distinguish parties who use the new regime strategically from those who treat it as an unwelcome procedural hurdle.
For specialist guidance on construction ADR compliance, mediation preparation and dispute strategy under the Gauteng Directive, consult a qualified practitioner through the Global Law Experts legal directory.
This article was produced by Global Law Experts. For specialist advice on this topic, contact Roelf Nel at RN Inc., a member of the Global Law Experts network.
posted 24 minutes ago
posted 51 minutes ago
posted 1 hour ago
posted 2 hours ago
posted 3 hours ago
posted 3 hours ago
posted 3 hours ago
posted 4 hours ago
posted 4 hours ago
posted 5 hours ago
posted 5 hours ago
posted 5 hours ago
No results available
Find the right Legal Expert for your business
Sign up for the latest legal briefings and news within Global Law Experts’ community, as well as a whole host of features, editorial and conference updates direct to your email inbox.
Naturally you can unsubscribe at any time.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Global Law Experts is dedicated to providing exceptional legal services to clients around the world. With a vast network of highly skilled and experienced lawyers, we are committed to delivering innovative and tailored solutions to meet the diverse needs of our clients in various jurisdictions.
Send welcome message